3139 S HUTCHISON AVE 90034
Certificate Information: 3139 S HUTCHISON AVE 90034
- Application / Permit
- 22010-10000-03747
- Plan Check / Job No.
- B22LA14790
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 4/6/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2022 | KEVIN MORALES |
| Corrections Issued | 8/18/2022 | KEVIN MORALES |
| Quality Review Completed | 8/22/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 10/20/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 11/1/2022 | KEVIN MORALES |
| Plan Check Approved | 1/3/2023 | KEVIN MORALES |
| Issued | 4/6/2023 | APPLICANT |
| CofO in Progress | 3/3/2025 | ARAM AVEDISIAN |
| No Progress | 3/13/2025 | KENNETH NAGLE |
| CofO in Progress | 3/13/2025 | KENNETH NAGLE |
| CofO in Progress | 3/13/2025 | KENNETH NAGLE |
| CofO in Progress | 4/30/2025 | ARAM AVEDISIAN |
| Permit Finaled | 5/1/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/1/2025 | RICHARD STEINBACH |
| CofO Issued | 5/1/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/22/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | JEANIE LAM |
| Sewer availability | Cleared | 8/22/2022 | JEANIE LAM |
| Specific Plan | Cleared | 8/23/2022 | KEVIN ARUCAN |
| Construction near power lines | Cleared | 10/12/2022 | RIDWAN HARDY |
| Community Plan Implem. Overlay | Cleared | 10/26/2022 | KYLE WINSTON |
| Low Impact Development | Cleared | 10/26/2022 | ROGELIO CORTES |
| Specific Plan | Cleared | 10/26/2022 | KYLE WINSTON |
| Roof/Waste drainage to street | Cleared | 10/27/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xia,, Ji; Lic. No.: C89014 | 260 S LOS ROBLES AVE, STE 100 PASADENA, CA 91101 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/31/2023 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 8/31/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 9/6/2023 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 9/6/2023 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/17/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 11/17/2023 | Partial Approval | MEL KHACHATOURIAN |
| MERV13>=Rough | 11/17/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 11/17/2023 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 11/17/2023 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 11/27/2023 | Conditional Approval | BEN MOLSTAD |
| HVAC-Rough | 11/27/2023 | Corrections Issued | BEN MOLSTAD |
| MERV13>=Rough | 11/27/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 12/1/2023 | Conditional Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 12/1/2023 | Partial Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 12/13/2023 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 6/6/2024 | Approved | MEL KHACHATOURIAN |
| Final | 6/6/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| MERV13>=Final | 6/6/2024 | Approved | MEL KHACHATOURIAN |
| MERV13>=Rough | 6/6/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Service/Power Release | 6/6/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Smoke Detectors | 6/6/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 8/30/2024 | Corrections Issued | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Service/Power Release | 8/30/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Smoke Detectors | 8/30/2024 | Approved | MEL KHACHATOURIAN |
| Final | 2/19/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Service/Power Release | 2/19/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 3/3/2025 | Partial Approval | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/3/2025 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 3/3/2025 | Approved | ARAM AVEDISIAN |
| Final | 3/13/2025 | Corrections Issued | ARAM AVEDISIAN |
| Final | 4/30/2025 | OK to Issue CofO | ARAM AVEDISIAN |