1331 W 77TH ST 90044
Certificate Information: 1331 W 77TH ST 90044
- Application / Permit
- 22010-10000-03737
- Plan Check / Job No.
- B22LA14726
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: New 2-story addition to a 1 story Single Family Dwelling. 65 sq.ft. addition to 1st floor & 569 sq.ft. addition to 2nd floor.
- Permit Issued
- Issued on 9/1/2023
- Issuing Office
- Current Status
- CofO in Progress on 12/19/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2022 | HANS SANTIAGO |
| Corrections Issued | 8/22/2022 | HANS SANTIAGO |
| Quality Review Completed | 8/23/2022 | LIPING TENG |
| Plan Check Approved | 8/29/2023 | ANDREW SANTIAGO |
| Issued | 9/1/2023 | APPLICANT |
| CofO in Progress | 12/19/2024 | JOHN QUINTANILLA |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/7/2022 | RUEL COLE |
| Low Impact Development | Cleared | 7/10/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 7/21/2023 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2023 | HUGO LOPEZ |
| Sewer availability | Cleared | 7/28/2023 | HUGO LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez,, Gerardo; Lic. No.: C78115 | 1426 E STUART AVE WEST COVINA, CA 91791 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/20/2023 | Conditional Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/2/2023 | No Access for Inspection | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/10/2023 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 10/16/2023 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2023 | Corrections Issued | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 1/2/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 1/2/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/4/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2024 | Partial Approval | ANTHONY EGSON |
| Insulation | 1/4/2024 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 2/13/2024 | Partial Approval | JOSE MACIAS |
| Deputy Wood Construction | 2/15/2024 | Conditional Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 2/16/2024 | Partial Approval | JOSE MACIAS |
| BUILDING-Rough-Frame | 2/29/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 4/4/2024 | No Access for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 4/4/2024 | No Access for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 4/8/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 4/8/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 5/2/2024 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 5/2/2024 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 5/2/2024 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 5/3/2024 | Corrections Issued | CRAIG DAVIS |
| Interior/Exterior Lathing | 5/22/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/24/2024 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 5/24/2024 | Approved | CRAIG DAVIS |
| HVAC-Rough | 5/24/2024 | Approved | CRAIG DAVIS |
| Insulation | 5/30/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 6/5/2024 | Approved | MICHAEL LEWIS |
| Shower Pan | 6/5/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 6/26/2024 | Approved | MICHAEL LEWIS |
| Deck | 7/2/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 11/21/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 11/21/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 11/21/2024 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 11/21/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 11/21/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 11/21/2024 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 11/21/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Final | 12/18/2024 | Approved | JOHN QUINTANILLA |
| Final | 12/18/2024 | OK to Issue CofO | JOHN QUINTANILLA |
| HVAC-Final | 12/18/2024 | Approved | JOHN QUINTANILLA |
| PLUMBING-Final | 12/18/2024 | Approved | JOHN QUINTANILLA |
| Smoke Detectors | 12/18/2024 | Approved | JOHN QUINTANILLA |
| Special/Order Compliance | 12/24/2024 | Corrections Issued | MICHAEL LEWIS |