917 E 98TH ST 90002

Certificate Information: 917 E 98TH ST 90002

Application / Permit
22010-10000-03711
Plan Check / Job No.
B22LA14627
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan NEW 20' X 20' DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 9/10/2022
Issuing Office
Current Status
Issued on 9/10/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/28/2022 APPLICANT
Assigned to Plan Check Engineer 8/5/2022 SELLA BENYAMIN
Corrections Issued 8/6/2022 SELLA BENYAMIN
Plan Check Approved 9/9/2022 SELLA BENYAMIN
Issued 9/10/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/24/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/24/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 8/24/2022 STEVE MELGAR
Sewer availability Cleared 8/24/2022 STEVE MELGAR
Construction near power lines Cleared 8/25/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/2/2022 Corrections Issued JOHN KLARIN
PLUMBING-Rough 11/2/2022 Corrections Issued JOHN KLARIN
Excavation/Setback/Form/Re-Bar 3/24/2023 Partial Approval JOHN KLARIN
PLUMBING-Rough 3/24/2023 Approved JOHN KLARIN
Footing/Foundation/Slab 5/12/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Partial Approval JAMES CHAVEZ
Verify Sprinkler Sign Off 6/20/2023 Not Ready for Inspection JAMES CHAVEZ
BUILDING-Rough-Frame 7/25/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 7/25/2023 Approved JOHN KLARIN
PLUMBING-Rough 7/25/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 7/25/2023 Approved JOHN KLARIN
Insulation 8/16/2023 Approved JOHN KLARIN
Drywall Nailing 9/27/2023 Approved JOHN KLARIN
Final 3/1/2024 Corrections Issued JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Approved JAMES CHAVEZ
Service/Power Release 3/1/2024 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 3/1/2024 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Final 3/20/2024 Conditional Approval BEN MOLSTAD
Final 3/20/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Final 3/20/2024 Approved BEN MOLSTAD
Final 11/18/2024 Not Ready for Inspection ANTHONY EGSON
Service/Power Release 11/18/2024 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 11/18/2024 No Access for Inspection ANTHONY EGSON