1121 N EMBURY ST 90272

Certificate Information: 1121 N EMBURY ST 90272

Application / Permit
22010-10000-03678
Plan Check / Job No.
B22LA14522
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(ePlan) NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 2/14/2023
Issuing Office
Current Status
CofO Issued on 4/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2022 APPLICANT
Assigned to Plan Check Engineer 8/4/2022 YOUNG KIM
Corrections Issued 8/9/2022 YOUNG KIM
Quality Review Completed 8/9/2022 GARO TELMI
Applicant returned to address corrections 10/31/2022 YOUNG KIM
Applicant returned to address corrections 11/10/2022 YOUNG KIM
Applicant returned to address corrections 12/15/2022 YOUNG KIM
Applicant returned to address corrections 12/16/2022 YOUNG KIM
Applicant returned to address corrections 1/20/2023 YOUNG KIM
Applicant returned to address corrections 1/23/2023 YOUNG KIM
Applicant returned to address corrections 1/27/2023 YOUNG KIM
Plan Check Approved 2/3/2023 YOUNG KIM
Issued 2/14/2023 APPLICANT
CofO in Progress 3/29/2024 ARAM AVEDISIAN
Permit Finaled 4/2/2024 DANIEL ORRANTE
CofO Issued 4/2/2024 DANIEL ORRANTE
Permit Finaled 4/2/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/16/2022 JENSON LEE
Address approval Cleared 8/22/2022 JENSON LEE
Sewer availability Cleared 8/25/2022 JENSON LEE
Hydrant and Access approval Cleared 9/23/2022 MATTHEW CRAIG
Low Impact Development Cleared 9/30/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 10/5/2022 JENSON LEE
GPI Written Notices Cleared 10/31/2022 YOUNG KIM
Grading Pre-Inspection Cleared 10/31/2022 YOUNG KIM

Contact Information

Contractor Ortam Construction Inc; Lic. No.: 880225-B 4500 PARK GRANADA #202      CALABASAS, CA 91302
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/8/2023 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 5/8/2023 Corrections Issued OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 5/10/2023 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 5/10/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Reinf. Concrete 5/11/2023 Conditional Approval MICHAEL PELHAM
Sewer 5/15/2023 No Access for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/18/2023 Approved OGANES TARAKHCHYAN
Sewer 5/18/2023 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/1/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 6/13/2023 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/16/2023 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 7/20/2023 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 7/24/2023 Conditional Approval KEVIN SARGSYAN
HVAC-Rough 7/24/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 7/26/2023 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 7/27/2023 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 7/31/2023 Approved OGANES TARAKHCHYAN
Shower Pan 8/1/2023 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/4/2023 Approved OGANES TARAKHCHYAN
Green Building Rough 8/4/2023 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 8/4/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/8/2023 Partial Approval OGANES TARAKHCHYAN
Insulation 8/15/2023 Corrections Issued EVAN COOPER
Drywall Nailing 8/22/2023 Approved OGANES TARAKHCHYAN
Insulation 8/22/2023 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/28/2023 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 1/11/2024 Partial Approval ARAM AVEDISIAN
Underground Mechanical 1/11/2024 Partial Approval ARAM AVEDISIAN
HVAC-Final 1/18/2024 Conditional Approval MICHAEL PELHAM
PLUMBING-Final 1/23/2024 Corrections Issued KENNETH NAGLE
PLUMBING-Final 2/7/2024 Approved EVAN COOPER
Final 3/27/2024 Corrections Issued ARAM AVEDISIAN
Green Building Final 3/27/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/27/2024 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 3/27/2024 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 3/27/2024 Approved ARAM AVEDISIAN
Final 3/29/2024 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 3/29/2024 Approved ARAM AVEDISIAN