1238 1/2 S MEADOWBROOK AVE 90019

Certificate Information: 1238 1/2 S MEADOWBROOK AVE 90019

Application / Permit
22010-10000-03636
Plan Check / Job No.
B22LA14340
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERT EXISTING DETACHED GARAGE AND ADDITION TO CREATE 2 STORY ADU (749 SQ.FT.) per LAMC 12.22A.33(c)(d)
Permit Issued
Issued on 2/15/2023
Issuing Office
Current Status
CofO Issued on 11/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 MARCELA FRANQUEZ
Corrections Issued 8/30/2022 MARCELA FRANQUEZ
Quality Review Completed 9/7/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 11/22/2022 MARCELA FRANQUEZ
Plan Check Approved 1/24/2023 MARCELA FRANQUEZ
Issued 2/15/2023 APPLICANT
CofO in Progress 11/7/2023 RICHARD DOCKUS
Permit Finaled 11/21/2023 DEROLD HAUFF
CofO Issued 11/21/2023 DEROLD HAUFF
Permit Finaled 11/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 10/22/2022 RIDWAN HARDY
Construction within easement Cleared 10/22/2022 RIDWAN HARDY
CPC Cleared 11/14/2022 KENTON TRINH
Address approval Cleared 11/16/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 11/16/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 11/28/2022 TREVOR QUAN
Sewer availability Cleared 11/28/2022 TREVOR QUAN
HPOZ Cleared 11/29/2022 AMANDA KAINER
Tenant Habitability Plan Cleared 12/13/2022 ISMAEL HERNANDEZ

Contact Information

Contractor L A Developing Inc; Lic. No.: 1083426-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/24/2023 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 5/1/2023 Corrections Issued RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 5/8/2023 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 5/11/2023 Approved RICHARD DOCKUS
METHANE-Barrier 5/11/2023 Approved RICHARD DOCKUS
METHANE-Subgrade 5/11/2023 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 5/25/2023 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Partial Approval RICHARD DOCKUS
Deputy Wood Construction 6/23/2023 Conditional Approval RICHARD DOCKUS
ELECTRICAL-Rough 6/27/2023 Approved RICHARD DOCKUS
PLUMBING-Rough 6/27/2023 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 6/29/2023 Approved RICHARD DOCKUS
Green Building Rough 6/29/2023 Approved RICHARD DOCKUS
HVAC-Rough 6/29/2023 Approved RICHARD DOCKUS
METHANE-Rough 6/29/2023 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Approved LILIANA PORTILLO
Insulation 7/11/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/11/2023 Partial Approval LILIANA PORTILLO
Drywall Nailing 7/14/2023 Partial Approval LILIANA PORTILLO
Drywall Nailing 9/13/2023 Approved RICHARD DOCKUS
Final 9/13/2023 Corrections Issued RICHARD DOCKUS
Green Building Final 9/13/2023 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 9/13/2023 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 9/13/2023 Approved RICHARD DOCKUS
Final 9/29/2023 Not Ready for Inspection RICHARD DOCKUS
Final 10/5/2023 Not Ready for Inspection RICHARD DOCKUS
Final 10/20/2023 Not Ready for Inspection RICHARD DOCKUS
Final 11/2/2023 OK to Issue CofO RICHARD DOCKUS