5650 N VESPER AVE 91411

Certificate Information: 5650 N VESPER AVE 91411

Application / Permit
22010-10000-03631
Plan Check / Job No.
B22LA14336
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO DETACHED GARAGE FOR NEW ADU 635 SQ. FT. ADU CHECKED PER LAMC 12.22 A.33(C) AND (D)
Permit Issued
Issued on 4/3/2023
Issuing Office
Current Status
Issued on 4/3/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/21/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 JOE VO
Corrections Issued 7/29/2022 SUNMIN LEE
Plan Check Approved 4/3/2023 JOE VO
Issued 4/3/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/4/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 11/9/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 11/9/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 2/2/2023 RIDWAN HARDY
Low Impact Development Cleared 3/29/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 3/31/2023 JEANIE LAM

Contact Information

Contractor M & D Contractors Inc; Lic. No.: 931922-B       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/28/2023 Partial Inspection RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 6/27/2023 Partial Approval RYAN SALAZAR
PLUMBING-Rough 7/13/2023 Partial Approval RYAN SALAZAR
Underground Mechanical 7/13/2023 Approved RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 7/21/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/21/2023 Not Ready for Inspection JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 7/28/2023 Conditional Approval RYAN SALAZAR
Deputy Wood Construction 2/6/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 2/9/2024 Partial Approval RYAN SALAZAR
Green Building Rough 2/9/2024 Not Ready for Inspection RYAN SALAZAR
Verify Sprinkler Sign Off 2/9/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 2/22/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 2/22/2024 Approved RYAN SALAZAR
Green Building Rough 2/22/2024 Approved RYAN SALAZAR
PLUMBING-Rough 2/22/2024 Approved RYAN SALAZAR
Insulation 6/13/2024 Approved RYAN SALAZAR
Drywall Nailing 7/29/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/29/2024 Approved MICHEL ABAJAN
Shower Pan 9/13/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/21/2024 Approved MATTHEW NELSON
Final 5/13/2025 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 5/13/2025 Approved RYAN SALAZAR
Green Building Final 5/13/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/13/2025 SGSOV Approved RYAN SALAZAR
Service/Power Release 5/13/2025 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 5/13/2025 Approved RYAN SALAZAR
Final 7/18/2025 Partial Approval RYAN SALAZAR
Service/Power Release 7/18/2025 Approved RYAN SALAZAR