1032 N OXFORD AVE 90029

Certificate Information: 1032 N OXFORD AVE 90029

Application / Permit
22010-10000-03628
Plan Check / Job No.
B22LA10517
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Building D - (N) 2 Story Detached ADU ADU PER 12.22 (c) & (d) 4 of 4
Permit Issued
Issued on 9/19/2023
Issuing Office
Current Status
CofO Issued on 10/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 ADRIANA LOPEZ
Corrections Issued 7/21/2022 ADRIANA LOPEZ
Quality Review Completed 7/29/2022 FARUK SEZER
Applicant returned to address corrections 1/31/2023 ADRIANA LOPEZ
Applicant returned to address corrections 5/9/2023 ADRIANA LOPEZ
Applicant returned to address corrections 7/5/2023 ADRIANA LOPEZ
Applicant returned to address corrections 7/12/2023 ADRIANA LOPEZ
Plan Check Approved 7/20/2023 ADRIANA LOPEZ
Issued 9/19/2023 APPLICANT
CofO in Progress 10/16/2025 RAUL BARAJAS
Permit Finaled 10/17/2025 DEROLD HAUFF
CofO Issued 10/17/2025 DEROLD HAUFF
Permit Finaled 10/17/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/18/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 8/19/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 8/19/2022 CHRISTOPHER ROCHA
Hydrant and Access approval Cleared 11/4/2022 LAVEON RIDER
Tenant Habitability Plan Cleared 1/27/2023 MICHAEL SOTO
Low Impact Development Cleared 5/13/2023 TA ANH
Roof/Waste drainage to street Cleared 6/1/2023 JEANIE LAM

Contact Information

Contractor J Z J B Cnst Inv; Lic. No.: 1013600-B       ,
Engineer Desai,, Anil T; Lic. No.: C24653 1530 VIA LOS COYOTES      LA HABRA, CA 90631
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/26/2023 Approved JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 1/19/2024 Approved JEFFREY MEAD
Footing/Foundation/Slab 1/19/2024 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 3/6/2024 Partial Approval JEFFREY MEAD
PLUMBING-Rough 4/18/2024 Corrections Issued AMIR NAZARIAN
Gas Test 5/10/2024 Partial Approval JEFFREY MEAD
PLUMBING-Rough 5/10/2024 Not Ready for Inspection JEFFREY MEAD
Underground Mechanical 5/10/2024 Approved JEFFREY MEAD
Sewer 5/17/2024 Approved JEFFREY MEAD
ELECTRICAL-Rough 6/27/2024 Approved JOSEPH MCGARRY
HVAC-Rough 6/27/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 7/12/2024 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 7/12/2024 Not Ready for Inspection ENRIQUE MIRELES
MERV13>=Rough 7/12/2024 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 7/12/2024 Not Ready for Inspection ENRIQUE MIRELES
Deputy Wood Construction 7/15/2024 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 7/19/2024 Approved ENRIQUE MIRELES
Green Building Rough 7/19/2024 Approved ENRIQUE MIRELES
MERV13>=Rough 7/19/2024 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 7/19/2024 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 8/5/2024 Partial Approval JEFFREY MEAD
Insulation 8/19/2024 Corrections Issued JEFFREY MEAD
Insulation 8/26/2024 Approved NICHOLAS LOPEZ
Drywall Nailing 9/5/2024 Approved NICHOLAS LOPEZ
Shower Pan 9/5/2024 Not Ready for Inspection NICHOLAS LOPEZ
Shower Pan 9/9/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 10/28/2024 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 4/9/2025 Corrections Issued JEFFREY MEAD
Service/Power Release 5/1/2025 Approved JEFFREY MEAD
Final 8/8/2025 Not Ready for Inspection JEFFREY MEAD
Green Building Final 8/8/2025 Approved JEFFREY MEAD
MERV13>=Final 8/8/2025 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 8/8/2025 Not Ready for Inspection JEFFREY MEAD
Final 8/14/2025 Corrections Issued JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 8/14/2025 SGSOV Approved JEFFREY MEAD
Smoke Detectors 8/14/2025 Approved JEFFREY MEAD
Final 8/20/2025 OK to Issue CofO JEFFREY MEAD