1032 N OXFORD AVE 90029
Certificate Information: 1032 N OXFORD AVE 90029
- Application / Permit
- 22010-10000-03628
- Plan Check / Job No.
- B22LA10517
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Building D - (N) 2 Story Detached ADU ADU PER 12.22 (c) & (d) 4 of 4
- Permit Issued
- Issued on 9/19/2023
- Issuing Office
- Current Status
- CofO Issued on 10/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | ADRIANA LOPEZ |
| Corrections Issued | 7/21/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 7/29/2022 | FARUK SEZER |
| Applicant returned to address corrections | 1/31/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 5/9/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 7/5/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 7/12/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 7/20/2023 | ADRIANA LOPEZ |
| Issued | 9/19/2023 | APPLICANT |
| CofO in Progress | 10/16/2025 | RAUL BARAJAS |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
| CofO Issued | 10/17/2025 | DEROLD HAUFF |
| Permit Finaled | 10/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 8/19/2022 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 11/4/2022 | LAVEON RIDER |
| Tenant Habitability Plan | Cleared | 1/27/2023 | MICHAEL SOTO |
| Low Impact Development | Cleared | 5/13/2023 | TA ANH |
| Roof/Waste drainage to street | Cleared | 6/1/2023 | JEANIE LAM |
Contact Information
| Contractor | J Z J B Cnst Inv; Lic. No.: 1013600-B | , |
| Engineer | Desai,, Anil T; Lic. No.: C24653 | 1530 VIA LOS COYOTES LA HABRA, CA 90631 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/26/2023 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 1/19/2024 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 1/19/2024 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2024 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 4/18/2024 | Corrections Issued | AMIR NAZARIAN |
| Gas Test | 5/10/2024 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 5/10/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Underground Mechanical | 5/10/2024 | Approved | JEFFREY MEAD |
| Sewer | 5/17/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 6/27/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 6/27/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/12/2024 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 7/12/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| MERV13>=Rough | 7/12/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 7/12/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Deputy Wood Construction | 7/15/2024 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 7/19/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 7/19/2024 | Approved | ENRIQUE MIRELES |
| MERV13>=Rough | 7/19/2024 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 7/19/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/5/2024 | Partial Approval | JEFFREY MEAD |
| Insulation | 8/19/2024 | Corrections Issued | JEFFREY MEAD |
| Insulation | 8/26/2024 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 9/5/2024 | Approved | NICHOLAS LOPEZ |
| Shower Pan | 9/5/2024 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Shower Pan | 9/9/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 10/28/2024 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 4/9/2025 | Corrections Issued | JEFFREY MEAD |
| Service/Power Release | 5/1/2025 | Approved | JEFFREY MEAD |
| Final | 8/8/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 8/8/2025 | Approved | JEFFREY MEAD |
| MERV13>=Final | 8/8/2025 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 8/8/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 8/14/2025 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 8/14/2025 | Approved | JEFFREY MEAD |
| Final | 8/20/2025 | OK to Issue CofO | JEFFREY MEAD |