17624 W CALVERT ST 91316
Certificate Information: 17624 W CALVERT ST 91316
- Application / Permit
- 22010-10000-03617
- Plan Check / Job No.
- B22LA14314
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan (n) 1-story detached ADU per LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 3/6/2023
- Issuing Office
- Current Status
- CofO Issued on 1/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | KELVIN CHUONG |
| Corrections Issued | 8/25/2022 | KELVIN CHUONG |
| Quality Review Completed | 8/30/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/23/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 2/17/2023 | KELVIN CHUONG |
| Plan Check Approved | 3/3/2023 | KELVIN CHUONG |
| No Progress | 3/3/2023 | KELVIN CHUONG |
| Plan Check Approved | 3/3/2023 | KELVIN CHUONG |
| Issued | 3/6/2023 | APPLICANT |
| CofO in Progress | 12/29/2023 | JON MCHUGH |
| Permit Finaled | 1/18/2024 | JOHN JANSON |
| CofO Issued | 1/18/2024 | JOHN JANSON |
| Permit Finaled | 1/18/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/30/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 10/17/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 10/17/2022 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 10/17/2022 | COLIN LOREDO |
| ZI | Cleared | 10/18/2022 | LOUIS ORTEGA |
| Low Impact Development | Cleared | 12/13/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 12/19/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 12/19/2022 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 12/19/2022 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 12/19/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/19/2023 | Corrections Issued | SEAN WIRCH |
| Underground Mechanical | 7/19/2023 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 7/28/2023 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 9/6/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 9/6/2023 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Partial Approval | JON MCHUGH |
| HVAC-Rough | 9/6/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 9/6/2023 | Partial Approval | JON MCHUGH |
| Sewer | 9/6/2023 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 9/6/2023 | Approved | JON MCHUGH |
| Wood Frame | 9/6/2023 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Rough | 9/19/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 9/19/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 9/25/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 9/25/2023 | Approved | JON MCHUGH |
| HVAC-Rough | 9/25/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 9/25/2023 | Partial Approval | JON MCHUGH |
| Insulation | 9/27/2023 | Approved | JON MCHUGH |
| Drywall Nailing | 10/11/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 10/11/2023 | Approved | JON MCHUGH |
| Shower Pan | 10/11/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 11/16/2023 | Approved | JON MCHUGH |
| Gas Test | 11/16/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 11/21/2023 | Corrections Issued | JON MCHUGH |
| Final | 11/21/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 11/21/2023 | Approved | JON MCHUGH |
| HVAC-Final | 11/21/2023 | Approved | JON MCHUGH |
| PLUMBING-Final | 11/21/2023 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 11/21/2023 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 11/21/2023 | Approved | JON MCHUGH |
| Final | 12/7/2023 | Corrections Issued | JON MCHUGH |
| Service/Power Release | 12/7/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 12/29/2023 | Approved | JON MCHUGH |
| Final | 12/29/2023 | OK to Issue CofO | JON MCHUGH |
| PLUMBING-Final | 12/29/2023 | Approved | JON MCHUGH |
| Service/Power Release | 12/29/2023 | Approved | JON MCHUGH |