20937 S DENKER AVE 90501
Certificate Information: 20937 S DENKER AVE 90501
- Application / Permit
- 22010-10000-03610
- Plan Check / Job No.
- B22LA14308
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan New detached ADU in REAR. DETACHED ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 7/27/2024
- Issuing Office
- Current Status
- CofO Issued on 3/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | ADRIANA LOPEZ |
| Corrections Issued | 9/1/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 9/2/2022 | GARO TELMI |
| Applicant returned to address corrections | 4/10/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 5/23/2024 | ADRIANA LOPEZ |
| Issued | 7/27/2024 | APPLICANT |
| CofO in Progress | 3/21/2025 | EUGENE CASSIDY |
| Permit Finaled | 3/21/2025 | ANSON MAGLASANG |
| CofO Issued | 3/21/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/28/2023 | KURT CORRAL |
| Address approval | Cleared | 4/14/2023 | KHAING AYE |
| Construction near power lines | Cleared | 8/1/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/1/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/12/2023 | LUIS LUVANO |
| Eng Process Fee Ord 176,300 | Cleared | 2/29/2024 | JILVER MAZARIEGOS |
| Roof/Waste drainage to street | Cleared | 2/29/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 3/1/2024 | KHAING AYE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: NA69472 | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/28/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/28/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 8/28/2024 | Corrections Issued | EUGENE CASSIDY |
| Sewer | 8/28/2024 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 8/28/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 9/4/2024 | Corrections Issued | EUGENE CASSIDY |
| Sewer | 9/4/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Underground Mechanical | 9/4/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Sewer | 9/10/2024 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 9/10/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/13/2024 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 9/13/2024 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 9/27/2024 | SGSOV Not Ready | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/17/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Partial Approval | EUGENE CASSIDY |
| Gas Test | 10/17/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 10/17/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Underground Mechanical | 10/17/2024 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 10/17/2024 | Corrections Issued | EUGENE CASSIDY |
| Deputy Wood Construction | 10/22/2024 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/28/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/28/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Approved | EUGENE CASSIDY |
| Gas Test | 10/28/2024 | Approved | EUGENE CASSIDY |
| Green Building Rough | 10/28/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 10/28/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/28/2024 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 10/28/2024 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 10/28/2024 | Approved | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 10/28/2024 | Approved | EUGENE CASSIDY |
| Insulation | 11/4/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 11/13/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/13/2024 | Approved | EUGENE CASSIDY |
| Shower Pan | 11/13/2024 | Corrections Issued | EUGENE CASSIDY |
| Shower Pan | 11/18/2024 | Approved | BEN MOLSTAD |
| Gas Test | 12/30/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 12/30/2024 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 12/30/2024 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 1/6/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Underground Mechanical | 1/6/2025 | Partial Approval | EUGENE CASSIDY |
| Service/Power Release | 1/10/2025 | Corrections Issued | EUGENE CASSIDY |
| Final | 2/6/2025 | Corrections Issued | EUGENE CASSIDY |
| Gas Test | 2/6/2025 | Approved | EUGENE CASSIDY |
| Green Building Final | 2/6/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 2/6/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/6/2025 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 2/6/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 2/6/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 3/4/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 3/4/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 3/4/2025 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 3/4/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 3/4/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 3/20/2025 | OK to Issue CofO | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 3/20/2025 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 3/20/2025 | Not Required | EUGENE CASSIDY |
| Smoke Detectors | 3/20/2025 | Approved | EUGENE CASSIDY |