1040 1/2-1/4 E 43RD ST 90011
Certificate Information: 1040 1/2-1/4 E 43RD ST 90011
- Application / Permit
- 22010-10000-03607
- Plan Check / Job No.
- B22LA14285
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY TWO UNITS OF ADU WITH WOOD FRAME PRESCRIPTIVE PROVISIONS (WFPP). CA GOVT. CODE 65858.2(e) (1) (D) AND APPLICABLE PART OF LAMC 12.22A 33.(c)-(d), (g) SEE COMMENT.
- Permit Issued
- Issued on 8/22/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | TSE MING HUANG |
| Corrections Issued | 8/2/2022 | TSE MING HUANG |
| Quality Review Completed | 8/5/2022 | KEN GILL |
| Building Plans Picked Up | 8/8/2022 | APPLICANT |
| Plan Check Approved | 2/13/2023 | TSE MING HUANG |
| Issued | 8/22/2023 | APPLICANT |
| CofO in Progress | 7/15/2024 | ALEJANDRO DE ARTOLA |
| CofO Issued | 7/24/2024 | DEROLD HAUFF |
| Permit Finaled | 7/24/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/8/2022 | AMAAN MALIK |
| Construction near power lines | Cleared | 10/1/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/1/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 11/29/2022 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 12/16/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 2/1/2023 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 2/7/2023 | JEANETTE VONG |
Contact Information
| Contractor | C S W F Construction Inc; Lic. No.: 1021458-B | 15831 SAN JOSE AVE LA PUENTE, CA 91744 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 11/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 11/3/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 11/15/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 11/21/2023 | Corrections Issued | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 11/29/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 12/12/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/21/2023 | No Access for Inspection | SABAS ALONSO |
| Wood Frame | 12/21/2023 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/8/2024 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 1/8/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Partial Approval | BRENDAN MORELLI |
| Insulation | 1/16/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 2/7/2024 | Conditional Approval | JOSE MACIAS |
| Interior/Exterior Lathing | 2/7/2024 | Conditional Approval | JOSE MACIAS |
| PLUMBING-Rough | 2/7/2024 | Not Ready for Inspection | JOSE MACIAS |
| BUILDING-Rough-Frame | 2/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 2/14/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/14/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 2/14/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 2/27/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/27/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/4/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 3/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 3/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 3/13/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/20/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 3/20/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 5/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 5/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/29/2024 | Approved | ALEJANDRO DE ARTOLA |
| Gas Test | 5/29/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 5/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 5/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 5/29/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Final | 6/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 6/5/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/2/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/2/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/12/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |