10408 1/2 S HICKORY ST 90002

Certificate Information: 10408 1/2 S HICKORY ST 90002

Application / Permit
22010-10000-03600
Plan Check / Job No.
B22LA14248
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 1-STORY SFD WITH ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 5/26/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/21/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 MAHNAZ NOURHASHEMI
Corrections Issued 8/5/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 8/12/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 8/16/2022 APPLICANT
Plan Check Approved 5/2/2023 MAHNAZ NOURHASHEMI
Issued 5/26/2023 APPLICANT
CofO in Progress 4/12/2024 BEN MOLSTAD
Permit Finaled 4/25/2024 ANSON MAGLASANG
CofO Issued 4/25/2024 ANSON MAGLASANG
Permit Finaled 4/25/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/6/2022 JEANETTE VONG
Hydrant and Access approval Cleared 10/7/2022 RUEL COLE
Eng Process Fee Ord 176,300 Cleared 3/20/2023 JEANETTE VONG
Sewer availability Cleared 3/20/2023 JEANETTE VONG
Low Impact Development Cleared 3/31/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 4/14/2023 CINDY QI

Contact Information

Contractor Ebenezer Construction; Lic. No.: 657529-B 9214 MANZANAR AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/5/2023 Partial Approval JOHN KLARIN
Underground Mechanical 6/5/2023 Partial Approval JOHN KLARIN
PLUMBING-Rough 6/6/2023 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 6/21/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/17/2023 Not Ready for Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 Partial Approval JOHN KLARIN
Green Building Rough 8/17/2023 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 8/17/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 10/31/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 10/31/2023 Approved JAMES CHAVEZ
Insulation 11/6/2023 Corrections Issued JOHN KLARIN
Insulation 11/9/2023 Approved JOHN KLARIN
Drywall Nailing 11/27/2023 Approved JOHN KLARIN
Service/Power Release 12/8/2023 Approved JOHN KLARIN
PLUMBING-Rough 2/2/2024 Partial Approval JOHN KLARIN
Sewer 2/2/2024 Approved JOHN KLARIN
BUILDING-Rough-Frame 3/26/2024 Partial Approval ANSON MAGLASANG
ELECTRICAL-Final 3/26/2024 Approved ANSON MAGLASANG
Final 3/26/2024 Corrections Issued ANSON MAGLASANG
Footing/Foundation/Slab 3/26/2024 Approved ANSON MAGLASANG
Green Building Final 3/26/2024 Approved ANSON MAGLASANG
Green Building Rough 3/26/2024 Approved ANSON MAGLASANG
HVAC-Final 3/26/2024 Approved ANSON MAGLASANG
PLUMBING-Final 3/26/2024 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 3/26/2024 SGSOV Not Ready ANSON MAGLASANG
Service/Power Release 3/26/2024 Not Ready for Inspection ANSON MAGLASANG
Smoke Detectors 3/26/2024 Not Ready for Inspection ANSON MAGLASANG
Verify Sprinkler Sign Off 3/26/2024 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 4/1/2024 Approved BEN MOLSTAD
Final 4/1/2024 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Approved BEN MOLSTAD
Smoke Detectors 4/1/2024 Approved BEN MOLSTAD
Final 4/11/2024 OK to Issue CofO BEN MOLSTAD
Service/Power Release 4/11/2024 Approved BEN MOLSTAD