23523 W HATTERAS ST 91367
Certificate Information: 23523 W HATTERAS ST 91367
- Application / Permit
- 22010-10000-03563
- Plan Check / Job No.
- B22LA14176
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW HOME W/ ATTTACHED GARAGE
- Permit Issued
- Issued on 9/9/2022
- Issuing Office
- Current Status
- Issued on 9/9/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | JAD BASMA |
| Corrections Issued | 7/30/2022 | JAD BASMA |
| Quality Review Completed | 8/5/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 8/8/2022 | APPLICANT |
| Plan Check Approved | 9/9/2022 | JAD BASMA |
| Issued | 9/9/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 8/9/2022 | AMMAR ELTAWIL |
| Permit | Cleared | 8/9/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 8/10/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 8/16/2022 | MATTHEW CRAIG |
| Sewer availability | Cleared | 8/18/2022 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 8/19/2022 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 8/29/2022 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 8/29/2022 | JAD BASMA |
| Disturb/Remove Protected Trees | Cleared | 9/7/2022 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/11/2022 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 10/11/2022 | Approved | TROY SANDERS |
| Underground Mechanical | 10/11/2022 | Approved | TROY SANDERS |
| Deputy Reinf. Concrete | 10/13/2022 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 1/17/2023 | Approved | TROY SANDERS |
| HVAC-Rough | 1/17/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 1/17/2023 | Approved | TROY SANDERS |
| Shower Pan | 1/17/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/16/2023 | Approved | TROY SANDERS |
| Green Building Rough | 2/16/2023 | Approved | TROY SANDERS |
| Insulation | 2/16/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 2/16/2023 | Partial Approval | TROY SANDERS |
| Verify Sprinkler Sign Off | 2/16/2023 | Approved | TROY SANDERS |
| Gas Test | 11/3/2023 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Final | 11/3/2023 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Final | 11/3/2023 | Not Ready for Inspection | TROY SANDERS |
| Service/Power Release | 11/14/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 3/4/2024 | Approved | TROY SANDERS |
| HVAC-Final | 3/4/2024 | Approved | TROY SANDERS |
| PLUMBING-Final | 3/4/2024 | Approved | TROY SANDERS |