7533 N ENFIELD AVE 91335

Certificate Information: 7533 N ENFIELD AVE 91335

Application / Permit
22010-10000-03559
Plan Check / Job No.
B22LA14143
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLA: NEW 28' X 20' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) . WORK PER WFPP. SEE COMMENTS
Permit Issued
Issued on 10/9/2022
Issuing Office
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2022 APPLICANT
Assigned to Plan Check Engineer 8/5/2022 JEROME MAGAT PALMA
Corrections Issued 8/6/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 9/23/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 9/28/2022 JEROME MAGAT PALMA
Plan Check Approved 10/4/2022 ALFRED RAMIREZ
Issued 10/9/2022 APPLICANT
CofO in Progress 8/8/2024 JEFFREY BULL
Permit Finaled 10/25/2024 JOHN JANSON
CofO Issued 10/25/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/9/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/15/2022 COLIN LOREDO
Sewer availability Cleared 8/15/2022 COLIN LOREDO
Low Impact Development Cleared 9/19/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 9/20/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/17/2022 Approved TROY SANDERS
Footing/Foundation/Slab 11/9/2022 Not Ready for Inspection JEFFREY BULL
PLUMBING-Rough 11/9/2022 Partial Approval JEFFREY BULL
Pre-Inspection 11/9/2022 Approved JEFFREY BULL
BUILDING-Rough-Frame 12/12/2022 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 12/12/2022 Approved JEFFREY BULL
Verify Sprinkler Sign Off 12/12/2022 Approved JEFFREY BULL
Footing/Foundation/Slab 2/23/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 2/23/2023 Partial Approval JEFFREY BULL
PLUMBING-Rough 2/23/2023 Not Ready for Inspection JEFFREY BULL
BUILDING-Rough-Frame 4/11/2023 No Access for Inspection JEFFREY BULL
Drywall Nailing 4/11/2023 No Access for Inspection JEFFREY BULL
Final 4/11/2023 No Access for Inspection JEFFREY BULL
Interior/Exterior Lathing 4/11/2023 No Access for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 4/11/2023 SGSOV Not Ready JEFFREY BULL
Service/Power Release 4/11/2023 No Access for Inspection JEFFREY BULL
Smoke Detectors 4/11/2023 No Access for Inspection JEFFREY BULL
BUILDING-Rough-Frame 4/14/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 4/14/2023 Approved JEFFREY BULL
Footing/Foundation/Slab 4/14/2023 Approved JEFFREY BULL
Green Building Rough 4/14/2023 Approved JEFFREY BULL
HVAC-Rough 4/14/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 4/14/2023 Partial Approval JEFFREY BULL
PLUMBING-Rough 4/14/2023 Approved JEFFREY BULL
Insulation 4/18/2023 Approved JEFFREY BULL
Drywall Nailing 5/19/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 9/1/2023 Approved JEFFREY BULL
Service/Power Release 1/29/2024 Approved JEFFREY BULL
Final 2/29/2024 Corrections Issued HENRY KIM
Gas Test 2/29/2024 Not Ready for Inspection HENRY KIM
SGSOV-Seismic Gas S/O Valve 2/29/2024 SGSOV Not Ready HENRY KIM
Smoke Detectors 2/29/2024 Not Ready for Inspection HENRY KIM
Gas Test 3/7/2024 Approved JEFFREY BULL
Pre-Inspection 5/10/2024 Approved JEFFREY BULL
Final 5/31/2024 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 5/31/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 5/31/2024 Approved JEFFREY BULL
Final 8/8/2024 OK to Issue CofO JEFFREY BULL
Special/Order Compliance 8/27/2024 Corrections Issued JEFFREY BULL