8333 W 4TH ST 90048

Certificate Information: 8333 W 4TH ST 90048

Application / Permit
22010-10000-03557
Plan Check / Job No.
B22LA14139
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: (N) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 1/18/2024
Issuing Office
Current Status
Issued on 1/18/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/4/2022 APPLICANT
Assigned to Plan Check Engineer 8/12/2022 DANIEL YIP
Corrections Issued 8/15/2022 DANIEL YIP
Quality Review Completed 8/16/2022 GARO TELMI
Plan Check Approved 12/5/2023 DANIEL YIP
No Progress 1/18/2024 DANIEL YIP
Plan Check Approved 1/18/2024 DANIEL YIP
Issued 1/18/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/26/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/29/2022 WALLIE JONG
Low Impact Development Cleared 12/16/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 12/19/2022 WALLIE JONG
Sewer availability Cleared 12/21/2022 WALLIE JONG
Hydrant and Access approval Cleared 11/1/2023 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Amoli,, Bahar Hosseini; Lic. No.: C94992 3221 CARTER AVE, APT 282      MARINA DEL REY, CA 90292
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 6/8/2026   

Inspection Request History

Footing/Foundation/Slab 5/1/2024 Partial Approval SEAN HAUPT
METHANE-Barrier 5/1/2024 Partial Approval SEAN HAUPT
METHANE-Subgrade 5/1/2024 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Partial Approval MEL KHACHATOURIAN
Green Building Rough 5/20/2024 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Rough 5/20/2024 No Access for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 5/20/2024 Not Ready for Inspection MEL KHACHATOURIAN
Special/Order Compliance 5/28/2024 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 6/12/2024 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 8/15/2024 Corrections Issued MEL KHACHATOURIAN
Green Building Rough 8/15/2024 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Rough 8/15/2024 Not Ready for Inspection MEL KHACHATOURIAN
Special/Order Compliance 8/15/2024 Not Ready for Inspection DANIEL VERA
Verify Sprinkler Sign Off 8/15/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 8/21/2024 Not Ready for Inspection SEAN HAUPT
Green Building Rough 8/21/2024 Not Ready for Inspection SEAN HAUPT
METHANE-Rough 8/21/2024 Not Ready for Inspection SEAN HAUPT
Verify Sprinkler Sign Off 8/21/2024 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Rough 8/26/2024 Not Ready for Inspection MEL KHACHATOURIAN
METHANE-Rough 8/26/2024 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 8/26/2024 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 9/16/2024 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 10/8/2024 Corrections Issued MEL KHACHATOURIAN
Green Building Rough 10/8/2024 Approved MEL KHACHATOURIAN
METHANE-Rough 10/8/2024 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 10/8/2024 Not Ready for Inspection MEL KHACHATOURIAN
Deputy Wood Construction 10/10/2024 No Access for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Partial Approval MEL KHACHATOURIAN
Verify Sprinkler Sign Off 10/11/2024 Not Ready for Inspection MEL KHACHATOURIAN
Interior/Exterior Lathing 10/18/2024 Not Ready for Inspection MEL KHACHATOURIAN
Rough-Elec/Plmb/HVAC 10/23/2024 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 10/23/2024 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 10/25/2024 Corrections Issued MEL KHACHATOURIAN
BUILDING-Rough-Frame 10/29/2024 Partial Approval MEL KHACHATOURIAN
Insulation 11/13/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 12/12/2024 Partial Approval ARAM AVEDISIAN
Sewer 12/12/2024 Approved ARAM AVEDISIAN
Pre-Inspection 7/8/2025 Corrections Issued EVAN COOPER
Gas Test 8/8/2025 Not Ready for Inspection EVAN COOPER
Gas Test 8/12/2025 Approved EVAN COOPER
Pool/Spa Cover 8/19/2025 Not Ready for Inspection DANIEL VERA
Pool/Spa Cover 8/20/2025 Not Ready for Inspection MICHAEL ALLEN
Pre-Inspection 8/20/2025 Not Ready for Inspection MICHAEL ALLEN
Pre-Inspection 1/9/2026 Partial Inspection WILBER ROSALES
ELECTRICAL-Final 3/23/2026 Approved WILBER ROSALES
Service/Power Release 3/23/2026 Approved WILBER ROSALES
HVAC-Final 3/31/2026 Corrections Issued WILBER ROSALES
PLUMBING-Final 3/31/2026 Corrections Issued WILBER ROSALES
HVAC-Final 4/17/2026 Approved WILBER ROSALES
PLUMBING-Final 4/17/2026 Approved WILBER ROSALES
BUILDING-Rough-Frame 4/28/2026 Approved WILBER ROSALES
Drywall Nailing 4/28/2026 Approved WILBER ROSALES
Final 4/28/2026 Corrections Issued WILBER ROSALES
Footing/Foundation/Slab 4/28/2026 Approved WILBER ROSALES
Green Building Final 4/28/2026 Approved WILBER ROSALES
METHANE-Barrier 4/28/2026 Approved WILBER ROSALES
METHANE-Subgrade 4/28/2026 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 4/28/2026 SGSOV Approved WILBER ROSALES
Smoke Detectors 4/28/2026 Approved WILBER ROSALES
Final 5/18/2026 Not Ready for Inspection WILBER ROSALES
Final 6/4/2026 Not Ready for Inspection WILBER ROSALES