8333 W 4TH ST 90048
Certificate Information: 8333 W 4TH ST 90048
- Application / Permit
- 22010-10000-03557
- Plan Check / Job No.
- B22LA14139
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: (N) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 1/18/2024
- Issuing Office
- Current Status
- Issued on 1/18/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2022 | DANIEL YIP |
| Corrections Issued | 8/15/2022 | DANIEL YIP |
| Quality Review Completed | 8/16/2022 | GARO TELMI |
| Plan Check Approved | 12/5/2023 | DANIEL YIP |
| No Progress | 1/18/2024 | DANIEL YIP |
| Plan Check Approved | 1/18/2024 | DANIEL YIP |
| Issued | 1/18/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2022 | WALLIE JONG |
| Low Impact Development | Cleared | 12/16/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 12/19/2022 | WALLIE JONG |
| Sewer availability | Cleared | 12/21/2022 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 11/1/2023 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Amoli,, Bahar Hosseini; Lic. No.: C94992 | 3221 CARTER AVE, APT 282 MARINA DEL REY, CA 90292 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 6/8/2026 |
Inspection Request History
| Footing/Foundation/Slab | 5/1/2024 | Partial Approval | SEAN HAUPT |
| METHANE-Barrier | 5/1/2024 | Partial Approval | SEAN HAUPT |
| METHANE-Subgrade | 5/1/2024 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 5/20/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Rough | 5/20/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 5/20/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Special/Order Compliance | 5/28/2024 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 8/15/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Rough | 8/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Rough | 8/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Special/Order Compliance | 8/15/2024 | Not Ready for Inspection | DANIEL VERA |
| Verify Sprinkler Sign Off | 8/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 8/21/2024 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 8/21/2024 | Not Ready for Inspection | SEAN HAUPT |
| METHANE-Rough | 8/21/2024 | Not Ready for Inspection | SEAN HAUPT |
| Verify Sprinkler Sign Off | 8/21/2024 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 8/26/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Rough | 8/26/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 8/26/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2024 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/8/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Rough | 10/8/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 10/8/2024 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 10/8/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Deputy Wood Construction | 10/10/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Partial Approval | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 10/11/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 10/18/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Rough-Elec/Plmb/HVAC | 10/23/2024 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 10/23/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 10/25/2024 | Corrections Issued | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 10/29/2024 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 11/13/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 12/12/2024 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 12/12/2024 | Approved | ARAM AVEDISIAN |
| Pre-Inspection | 7/8/2025 | Corrections Issued | EVAN COOPER |
| Gas Test | 8/8/2025 | Not Ready for Inspection | EVAN COOPER |
| Gas Test | 8/12/2025 | Approved | EVAN COOPER |
| Pool/Spa Cover | 8/19/2025 | Not Ready for Inspection | DANIEL VERA |
| Pool/Spa Cover | 8/20/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Pre-Inspection | 8/20/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Pre-Inspection | 1/9/2026 | Partial Inspection | WILBER ROSALES |
| ELECTRICAL-Final | 3/23/2026 | Approved | WILBER ROSALES |
| Service/Power Release | 3/23/2026 | Approved | WILBER ROSALES |
| HVAC-Final | 3/31/2026 | Corrections Issued | WILBER ROSALES |
| PLUMBING-Final | 3/31/2026 | Corrections Issued | WILBER ROSALES |
| HVAC-Final | 4/17/2026 | Approved | WILBER ROSALES |
| PLUMBING-Final | 4/17/2026 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 4/28/2026 | Approved | WILBER ROSALES |
| Drywall Nailing | 4/28/2026 | Approved | WILBER ROSALES |
| Final | 4/28/2026 | Corrections Issued | WILBER ROSALES |
| Footing/Foundation/Slab | 4/28/2026 | Approved | WILBER ROSALES |
| Green Building Final | 4/28/2026 | Approved | WILBER ROSALES |
| METHANE-Barrier | 4/28/2026 | Approved | WILBER ROSALES |
| METHANE-Subgrade | 4/28/2026 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 4/28/2026 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 4/28/2026 | Approved | WILBER ROSALES |
| Final | 5/18/2026 | Not Ready for Inspection | WILBER ROSALES |
| Final | 6/4/2026 | Not Ready for Inspection | WILBER ROSALES |