15043 W VALLEYHEART DR 91403

Certificate Information: 15043 W VALLEYHEART DR 91403

Application / Permit
22010-10000-03551
Plan Check / Job No.
B22LA14110
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
eplan: New pool per standard plan # 268
Permit Issued
Issued on 11/14/2022
Issuing Office
Current Status
CofO Issued on 4/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2022 APPLICANT
Assigned to Plan Check Engineer 7/20/2022 LUKE GONZALES
Plan Check Approved 10/19/2022 RICARDO RAMIREZ
Issued 11/14/2022 APPLICANT
CofO in Progress 4/14/2023 THOMAS FINNILA
CofO in Progress 4/14/2023 THOMAS FINNILA
Permit Finaled 4/13/2024 RUBEN SALAS
CofO Issued 4/13/2024 RUBEN SALAS
Permit Finaled 4/13/2024 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 8/10/2022 DALIA MOKAYED
Low Impact Development Cleared 8/25/2022 CHRIS VONG

Contact Information

Contractor Pool Icons Inc; Lic. No.: 479446-C53       ,
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 11/18/2022 Corrections Issued THOMAS FINNILA
Pre-Gunite 12/2/2022 Approved JENNIFER RABUCHIN
Enclosure/Fence 1/24/2023 Corrections Issued THOMAS FINNILA
Enclosure/Fence 2/2/2023 Corrections Issued MATTHEW NELSON
Enclosure/Fence 2/7/2023 Approved THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 3/17/2023 Approved THOMAS FINNILA
Final 3/17/2023 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV Not Ready THOMAS FINNILA
Equipment Noise Level 3/23/2023 Approved FELIPE PENICHE
Final 3/30/2023 Corrections Issued JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 3/30/2023 SGSOV Not Ready JOHN COLEMAN
Deck 4/3/2023 Corrections Issued THOMAS FINNILA
Final 4/12/2023 OK to Issue CofO THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 4/12/2023 SGSOV Approved THOMAS FINNILA