4019 W 59TH PL 90043
Certificate Information: 4019 W 59TH PL 90043
- Application / Permit
- 22010-10000-03550
- Plan Check / Job No.
- B22LA14109
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- **ePlan**(N) Dettached Garage at rear of the lot with 1/2 bathroom with access from the exterior of the building only.
- Permit Issued
- Issued on 9/21/2023
- Issuing Office
- Current Status
- CofO Issued on 7/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/26/2022 | HANS SANTIAGO |
| Corrections Issued | 7/27/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 6/14/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 8/8/2023 | EDWIN ESPIN |
| Plan Check Approved | 8/9/2023 | EDWIN ESPIN |
| Issued | 9/21/2023 | APPLICANT |
| CofO in Progress | 7/23/2025 | RAUL BARAJAS |
| Permit Finaled | 7/24/2025 | DEROLD HAUFF |
| CofO Issued | 7/24/2025 | DEROLD HAUFF |
| Permit Finaled | 7/24/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/7/2022 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 12/5/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 12/6/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2022 | TREVOR QUAN |
| Construction within easement | Cleared | 3/1/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/24/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 6/4/2023 | ADRIAN SANCHEZ |
| GPI Written Notices | Cleared | 6/14/2023 | ANDREW SANTIAGO |
Contact Information
| Contractor | Coast Builders Group Inc; Lic. No.: 872035-B | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/24/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/26/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/31/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 12/12/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 12/21/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/21/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/17/2024 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 1/17/2024 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 5/15/2024 | Approved | JOSE MACIAS |
| Final | 5/15/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 5/15/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 5/15/2024 | Not Ready for Inspection | JOSE MACIAS |
| Smoke Detectors | 5/15/2024 | Corrections Issued | JOSE MACIAS |
| Final | 5/20/2024 | Corrections Issued | JOSE MACIAS |
| Service/Power Release | 5/20/2024 | Approved | JOSE MACIAS |
| Smoke Detectors | 5/20/2024 | Approved | JOSE MACIAS |
| Deputy Reinf. Concrete | 6/20/2024 | Approved | JOSE MACIAS |
| Deputy Shotcrete | 8/15/2024 | Conditional Approval | JOSE MACIAS |
| Final | 6/16/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Final | 7/14/2025 | Corrections Issued | WAYNE REGESTER |
| Final | 7/23/2025 | OK to Issue CofO | RAUL BARAJAS |