439 N ISLAND AVE 90744

Certificate Information: 439 N ISLAND AVE 90744

Application / Permit
22010-10000-03549
Plan Check / Job No.
B22LA14095
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED FOUR CAR GARAGE ON GROUND FLOOR & ADU AT THE SECOND FLOOR PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 10/18/2023
Issuing Office
Current Status
CofO Issued on 2/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 SERGIO GUTIERREZ
Corrections Issued 9/9/2022 SERGIO GUTIERREZ
Quality Review Completed 9/14/2022 KEN GILL
Building Plans Picked Up 9/20/2022 APPLICANT
Applicant returned to address corrections 8/10/2023 SERGIO GUTIERREZ
Plan Check Approved 10/18/2023 SERGIO GUTIERREZ
Issued 10/18/2023 APPLICANT
CofO in Progress 2/2/2026 EUGENE CASSIDY
Permit Finaled 2/6/2026 ANSON MAGLASANG
CofO Issued 2/6/2026 ANSON MAGLASANG
Permit Finaled 2/6/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/16/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 9/19/2022 ABEL CASILLAS
Sewer availability Cleared 9/19/2022 ABEL CASILLAS
Construction near power lines Cleared 10/4/2022 TINA MIRANDA
Hydrant and Access approval Cleared 10/7/2022 JOHN CONNEALLY
Clean Up Green Up Cleared 10/27/2022 YINGSHI HUANG
ZA Case Cleared 10/27/2022 YINGSHI HUANG
Low Impact Development Cleared 9/5/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 9/11/2023 ANA SORIANO

Contact Information

Contractor Jarh Builders Corporation; Lic. No.: 1074687-B 15740 PARAMOUNT BLVD #E      PARAMOUNT, CA 90723
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/28/2024 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 10/28/2024 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 11/4/2024 Corrections Issued EUGENE CASSIDY
METHANE-Barrier 11/4/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 11/4/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 11/15/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 11/15/2024 Corrections Issued EUGENE CASSIDY
METHANE-Rough 11/25/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 11/25/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 12/5/2024 Approved EUGENE CASSIDY
Footing/Foundation/Slab 12/16/2024 Approved EUGENE CASSIDY
METHANE-Barrier 12/16/2024 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/9/2025 Conditional Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 2/21/2025 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 2/21/2025 Partial Approval EUGENE CASSIDY
Green Building Rough 2/21/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 2/21/2025 Not Ready for Inspection EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 2/21/2025 Corrections Issued EUGENE CASSIDY
Verify Sprinkler Sign Off 2/21/2025 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 2/27/2025 Partial Approval EUGENE CASSIDY
Green Building Rough 2/27/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 2/27/2025 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 2/27/2025 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 2/27/2025 Approved EUGENE CASSIDY
Insulation 3/10/2025 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 3/10/2025 Partial Approval EUGENE CASSIDY
Drywall Nailing 3/26/2025 Approved EUGENE CASSIDY
Insulation 3/26/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 3/26/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/30/2025 SGSOV Not Ready EUGENE CASSIDY
Pre-Inspection 10/2/2025 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 1/29/2026 Approved EUGENE CASSIDY
Final 1/29/2026 Corrections Issued EUGENE CASSIDY
Green Building Final 1/29/2026 Approved EUGENE CASSIDY
Green Building Rough 1/29/2026 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/29/2026 SGSOV Approved EUGENE CASSIDY
Service/Power Release 1/29/2026 Not Required EUGENE CASSIDY
Smoke Detectors 1/29/2026 Approved EUGENE CASSIDY
ELECTRICAL-Final 2/2/2026 Approved EUGENE CASSIDY
Final 2/2/2026 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 2/2/2026 Approved EUGENE CASSIDY
PLUMBING-Final 2/2/2026 Approved EUGENE CASSIDY