5609 W FALLSGROVE ST 90016

Certificate Information: 5609 W FALLSGROVE ST 90016

Application / Permit
22010-10000-03530
Plan Check / Job No.
B22LA14013
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW TWO STORY DETACHED ACCESSORY BUILDING, RECREATION ROOM OVER THE STORAGE ROOM. See Comment.
Permit Issued
Issued on 10/20/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 TSE MING HUANG
Corrections Issued 8/22/2022 TSE MING HUANG
Quality Review Completed 8/24/2022 KEN GILL
Applicant returned to address corrections 6/22/2023 TSE MING HUANG
Plan Check Approved 7/25/2023 TSE MING HUANG
Issued 10/20/2023 APPLICANT
CofO in Progress 9/9/2025 LUIS CASTRO
No Progress 9/11/2025 DEROLD HAUFF
CofO in Progress 9/11/2025 DEROLD HAUFF
Permit Finaled 1/27/2026 DEROLD HAUFF
CofO Issued 1/27/2026 DEROLD HAUFF
Permit Finaled 1/27/2026 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 1/10/2023 RIDWAN HARDY
Construction within easement Cleared 1/10/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 2/13/2023 JEANIE LAM
Sewer availability Cleared 2/13/2023 JEANIE LAM
Hydrant and Access approval Cleared 3/10/2023 KURT CORRAL
Low Impact Development Cleared 3/23/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 3/24/2023 TREVOR QUAN
Grading Pre-Inspection Cleared 7/25/2023 TSE MING HUANG

Contact Information

Contractor Owner-Builder       ,
Engineer Wong,, Ariv N; Lic. No.: C55045 PO BOX 53364      IRVINE, CA 92619

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/1/2023 Partial Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 11/8/2023 Approved ANTHONY EGSON
Footing/Foundation/Slab 11/8/2023 Approved ANTHONY EGSON
Footing/Foundation/Slab 11/16/2023 Approved ANTHONY EGSON
PLUMBING-Rough 11/16/2023 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Approved ANTHONY EGSON
Green Building Rough 11/28/2023 Not Ready for Inspection ANTHONY EGSON
Verify Sprinkler Sign Off 11/28/2023 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/14/2023 Approved ANTHONY EGSON
Green Building Rough 12/14/2023 Not Ready for Inspection ANTHONY EGSON
Verify Sprinkler Sign Off 12/14/2023 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 1/4/2024 Approved ANTHONY EGSON
PLUMBING-Rough 1/4/2024 Approved ANTHONY EGSON
HVAC-Rough 1/8/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 1/9/2024 Approved ANTHONY EGSON
Green Building Rough 1/9/2024 Approved ANTHONY EGSON
Insulation 1/9/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 1/9/2024 Approved ANTHONY EGSON
Verify Sprinkler Sign Off 1/9/2024 Approved ANTHONY EGSON
Drywall Nailing 1/24/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 1/24/2024 Partial Approval ANTHONY EGSON
Sewer 1/31/2024 Approved ANTHONY EGSON
Underground Mechanical 1/31/2024 Approved ANTHONY EGSON
Underground Mechanical 2/12/2024 Partial Approval BRENDAN MORELLI
ELECTRICAL-Final 2/26/2024 Approved ANTHONY EGSON
HVAC-Final 2/26/2024 Approved ANTHONY EGSON
PLUMBING-Final 2/26/2024 Approved ANTHONY EGSON
Final 3/14/2024 Corrections Issued ANTHONY EGSON
Green Building Final 3/14/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Not Required ANTHONY EGSON
Service/Power Release 3/14/2024 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 3/14/2024 Approved ANTHONY EGSON
Final 9/20/2024 Corrections Issued ANTHONY EGSON
Service/Power Release 9/20/2024 Approved ANTHONY EGSON
Final 9/2/2025 Not Ready for Inspection LUIS CASTRO
Final 9/8/2025 OK to Issue CofO LUIS CASTRO