1142 N CHARM ACRES PL 90272
Certificate Information: 1142 N CHARM ACRES PL 90272
- Application / Permit
- 22010-10000-03529
- Plan Check / Job No.
- B22LA14012
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan (N) 2-STORY SFD W/ATTACHED 2-CAR GARAGE
- Permit Issued
- Issued on 4/19/2023
- Issuing Office
- Current Status
- CofO Issued on 1/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | ADRIANA LOPEZ |
| Corrections Issued | 8/8/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 8/8/2022 | GARO TELMI |
| Applicant returned to address corrections | 12/9/2022 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 3/13/2023 | MICHAEL PEREZ |
| Plan Check Approved | 3/30/2023 | ADRIANA LOPEZ |
| No Progress | 4/10/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 4/18/2023 | ADRIANA LOPEZ |
| Issued | 4/19/2023 | APPLICANT |
| CofO in Progress | 1/16/2024 | JESUS RODRIGUEZ |
| Permit Finaled | 1/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/17/2024 | DANIEL ORRANTE |
| CofO Issued | 1/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/1/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | JOSE HERNANDEZ |
| Low Impact Development | Cleared | 9/23/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 9/24/2022 | JOSE HERNANDEZ |
| Hydrant and Access approval | Cleared | 10/3/2022 | GILBERT URREA |
| GPI Written Notices | Cleared | 3/30/2023 | ADRIANA LOPEZ |
| Grading Pre-Inspection | Cleared | 3/30/2023 | ADRIANA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
| Engineer | Zhao,, Xiaoming; Lic. No.: C70068 | 13402 PARK DR CERRITOS, CA 90703 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/25/2023 | Approved | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/22/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 5/23/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 5/25/2023 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 5/30/2023 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/12/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/14/2023 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/21/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/21/2023 | Approved | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 7/24/2023 | Conditional Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 7/24/2023 | No Access for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/25/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/26/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/26/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 7/26/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/27/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/27/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/28/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/16/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 8/16/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 8/16/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 8/17/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 8/18/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 8/25/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 8/25/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 8/29/2023 | Not Ready for Inspection | KENNETH NAGLE |
| Special/Order Compliance | 8/29/2023 | Corrections Issued | KENNETH NAGLE |
| BUILDING-Rough-Frame | 9/1/2023 | Approved | KENNETH NAGLE |
| Drywall Nailing | 9/1/2023 | Approved | KENNETH NAGLE |
| Green Building Rough | 9/1/2023 | Approved | KENNETH NAGLE |
| Sewer | 10/5/2023 | Approved | KENNETH NAGLE |
| Sewer | 10/10/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 12/29/2023 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 1/2/2024 | Corrections Issued | MICHAEL PELHAM |
| Gas Test | 1/4/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 1/9/2024 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Not Ready | ARAM AVEDISIAN |
| ELECTRICAL-Final | 1/10/2024 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 1/10/2024 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/10/2024 | SGSOV Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 1/12/2024 | Approved | JESUS RODRIGUEZ |
| Final | 1/12/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 1/12/2024 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 1/12/2024 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 1/12/2024 | Approved | JESUS RODRIGUEZ |