525 S HEWITT ST 90013
Certificate Information: 525 S HEWITT ST 90013
- Application / Permit
- 22010-10000-03517
- Plan Check / Job No.
- B22LA13969
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (7) Carport
- Work Description
- NEW CARPORT WITH SOLAR PANELS
- Permit Issued
- Issued on 11/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | SINA KHOSRAVI |
| Corrections Issued | 8/2/2022 | SINA KHOSRAVI |
| Quality Review Completed | 8/8/2022 | CHARLES CHANG |
| Building Plans Picked Up | 8/8/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 9/2/2022 | APPLICANT |
| Applicant returned to address corrections | 9/23/2022 | SINA KHOSRAVI |
| Applicant returned to address corrections | 10/31/2022 | SINA KHOSRAVI |
| Plan Check Approved | 11/1/2022 | SINA KHOSRAVI |
| Issued | 11/2/2022 | APPLICANT |
| CofO in Progress | 3/4/2024 | RAFAEL ESPINOZA |
| CofO Issued | 3/4/2024 | ERNESTO CORRAL |
| Permit Finaled | 3/4/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| ZI | Cleared | 8/17/2022 | MAXFIELD VERMY |
| DAS Clearance | Cleared | 9/16/2022 | SINA KHOSRAVI |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2022 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 9/28/2022 | WALLIE JONG |
| City owned building/parcel | Cleared | 10/6/2022 | SINA KHOSRAVI |
| Hydrant and Access approval | Cleared | 10/18/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Konstruct Inc; Lic. No.: 1037235-B | 3964 BIXBY DR LA VERNE, CA 91750 |
| Engineer | Oesterreicher,, Andrew Evans; Lic. No.: C81428 | PO BOX 413 CARNELIAN BAY, CA 96140 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/7/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| METHANE-Barrier | 11/7/2022 | Approved | RAFAEL ESPINOZA |
| METHANE-Subgrade | 11/7/2022 | Approved | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 11/23/2022 | Approved | RAFAEL ESPINOZA |
| Final | 12/27/2022 | Conditional Approval | RAFAEL ESPINOZA |
| Green Building Final | 12/27/2022 | Approved | RAFAEL ESPINOZA |
| Green Building Rough | 12/27/2022 | Approved | RAFAEL ESPINOZA |
| METHANE-Final | 12/27/2022 | Approved | RAFAEL ESPINOZA |
| METHANE-Rough | 12/27/2022 | Approved | RAFAEL ESPINOZA |
| Reinforced Masonry Frame | 12/27/2022 | Approved | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV No Gas | RAFAEL ESPINOZA |
| Smoke Detectors | 12/27/2022 | Approved | RAFAEL ESPINOZA |
| Final | 3/4/2024 | OK to Issue CofO | RAFAEL ESPINOZA |