140 1/2 S RIVERA ST 90063
Certificate Information: 140 1/2 S RIVERA ST 90063
- Application / Permit
- 22010-10000-03513
- Plan Check / Job No.
- B22LA11312
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 6/14/2024
- Issuing Office
- Current Status
- Issued on 6/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | CARLOS MONTES |
| Corrections Issued | 7/16/2022 | CARLOS MONTES |
| Quality Review Completed | 7/20/2022 | GARO TELMI |
| Applicant returned to address corrections | 6/15/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 1/31/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 2/20/2024 | CARLOS MONTES |
| Applicant returned to address corrections | 5/8/2024 | CARLOS MONTES |
| Plan Check Approved | 6/7/2024 | CARLOS MONTES |
| Issued | 6/14/2024 | APPLICANT |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 3/24/2023 | NELSON RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 3/31/2023 | KIRK LINKLATER |
| Address approval | Cleared | 4/4/2023 | JEANIE LAM |
| Low Impact Development | Cleared | 12/22/2023 | ROGELIO CORTES |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2024 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 1/19/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 1/19/2024 | CHRISTINA BRACO |
| GPI Written Notices | Cleared | 1/30/2024 | CARLOS MONTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castro,, Ivan Garcia; Lic. No.: C84846 | 540 W SIERRA MADRE BLVD #5 SIERRA MADRE, CA 91024 |
| Geologist | Kaligi,, Adam Azad; Lic. No.: GEO9287 | 19197 GOLDEN VALLEY RD #709 SANTA CLARITA, CA 91387 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/9/2024 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/9/2024 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Barrier | 7/9/2024 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 7/9/2024 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 7/9/2024 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/17/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Barrier | 7/17/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Subgrade | 7/17/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/17/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Deputy Methane Barrier | 7/26/2024 | Conditional Approval | JOSH MEISTER |
| METHANE-Barrier | 7/26/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| METHANE-Subgrade | 7/26/2024 | Approved | ARTHUR NEGRETE |
| Deputy Methane Barrier | 8/1/2024 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 8/2/2024 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 8/2/2024 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2024 | Conditional Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 10/18/2024 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 10/22/2024 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 11/7/2024 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/20/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 11/20/2024 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 11/20/2024 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 11/20/2024 | Approved | FREDDIE RIVERA |
| Wood Frame | 11/20/2024 | Partial Inspection | FREDDIE RIVERA |
| Insulation | 11/27/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/27/2024 | Partial Approval | FREDDIE RIVERA |
| Drywall Nailing | 12/3/2024 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 12/3/2024 | Approved | FREDDIE RIVERA |
| Gas Test | 1/7/2025 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 1/7/2025 | Partial Approval | JUSTIN HAWLEY |
| Sewer | 1/14/2025 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 1/30/2025 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 8/26/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| HVAC-Final | 8/26/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| PLUMBING-Final | 8/26/2025 | Corrections Issued | WILLIAM SIERRA |
| Special/Order Compliance | 8/26/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Final | 8/28/2025 | Approved | FREDDIE RIVERA |
| HVAC-Final | 8/28/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 8/28/2025 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 8/28/2025 | Corrections Issued | FREDDIE RIVERA |
| Service/Power Release | 1/15/2026 | Partial Inspection | FREDDIE RIVERA |