2547 S MIDVALE AVE 90064
Certificate Information: 2547 S MIDVALE AVE 90064
- Application / Permit
- 22010-10000-03502
- Plan Check / Job No.
- B22LA13906
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY HOUSE
- Permit Issued
- Issued on 10/14/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 8/17/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 8/26/2022 | KEN GILL |
| Building Plans Picked Up | 8/26/2022 | APPLICANT |
| Plan Check Approved | 10/13/2022 | MARCELA FRANQUEZ |
| Issued | 10/14/2022 | APPLICANT |
| CofO in Progress | 10/31/2023 | CARLOS MATAMOROS |
| Permit Finaled | 10/31/2023 | DANIEL ORRANTE |
| CofO Issued | 10/31/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/31/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2022 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 8/30/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 8/30/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 9/1/2022 | LAVEON RIDER |
| Specific Plan | Cleared | 9/13/2022 | KEVIN ARUCAN |
| Low Impact Development | Cleared | 9/26/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 9/30/2022 | STEVE MELGAR |
| GPI Written Notices | Cleared | 10/13/2022 | MARCELA FRANQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/28/2022 | Partial Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 12/12/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 12/14/2022 | Approved | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 12/16/2022 | Conditional Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2023 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Partial Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 1/27/2023 | Conditional Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 3/16/2023 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/16/2023 | Corrections Issued | JOHNNY MIRANDA |
| Deputy Steel/Welding | 3/23/2023 | Conditional Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 3/29/2023 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 3/29/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 3/29/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/29/2023 | Approved | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 3/29/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 4/18/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 4/18/2023 | Partial Approval | JOHNNY MIRANDA |
| Shower Pan | 4/18/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 4/25/2023 | Conditional Approval | HERBERT GIRON |
| Drywall Nailing | 4/25/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 4/25/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 5/5/2023 | Approved | JEREMY TODD |
| Underground Mechanical | 7/6/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 9/27/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 9/28/2023 | Approved | BEN MOLSTAD |
| Gas Test | 10/3/2023 | Approved | BEN MOLSTAD |
| HVAC-Final | 10/4/2023 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 10/6/2023 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 10/10/2023 | Partial Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/18/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 10/18/2023 | Approved | JESUS PINEDA |
| Final | 10/18/2023 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 10/18/2023 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 10/18/2023 | Not Ready for Inspection | JESUS PINEDA |
| Smoke Detectors | 10/18/2023 | Approved | JESUS PINEDA |
| Final | 10/25/2023 | OK to Issue CofO | CARLOS MATAMOROS |
| Service/Power Release | 10/25/2023 | Approved | CARLOS MATAMOROS |