1404 N MARTEL AVE 90046
Certificate Information: 1404 N MARTEL AVE 90046
- Application / Permit
- 22010-10000-03485
- Plan Check / Job No.
- B21LA13061
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED ADU PER CA GOVT CODE 65852.2 (e)(1)(D) AND APPLICABLE PART OF LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 5/15/2023
- Issuing Office
- Current Status
- CofO Issued on 2/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | SERGIO GUTIERREZ |
| Green Plans Picked Up | 8/6/2021 | APPLICANT |
| Corrections Issued | 8/9/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 8/18/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 8/23/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 8/23/2021 | APPLICANT |
| Applicant returned to address corrections | 9/2/2021 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 9/30/2021 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 12/30/2021 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 4/18/2022 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 7/1/2022 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 7/7/2022 | SERGIO GUTIERREZ |
| Plan Check Approved | 10/5/2022 | SERGIO GUTIERREZ |
| Plan Check Approved | 5/11/2023 | SERGIO GUTIERREZ |
| Issued | 5/15/2023 | APPLICANT |
| CofO in Progress | 2/13/2024 | STUART CHAPMAN |
| CofO Issued | 2/29/2024 | DEROLD HAUFF |
| Permit Finaled | 2/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 7/28/2022 | MITESH PATEL |
| DAS Clearance | Cleared | 7/29/2022 | SERGIO GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 8/2/2022 | STEVE MELGAR |
| Address approval | Cleared | 8/3/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 8/3/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 8/12/2022 | MATTHEW CRAIG |
| Tenant Habitability Plan | Cleared | 9/8/2022 | MICHAEL SOTO |
| Green Code | Cleared | 10/5/2022 | SERGIO GUTIERREZ |
Contact Information
| Contractor | Helio Group; Lic. No.: 1004478-B | 8721 SANTA MONICA BLVD STE 224 LOS ANGELES, CA 90069 |
| Engineer | Jahani,, Fereidoun; Lic. No.: C62875 | 3720 BLANCHE ST PASADENA, CA 91107 |
| Engineer | Saljooghi,, Sanjar; Lic. No.: C53610 | 23265 PARK ENSENADA CALABASAS, CA 91302 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/24/2023 | Partial Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 7/6/2023 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 7/6/2023 | Corrections Issued | STUART CHAPMAN |
| Underground Mechanical | 7/6/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 7/18/2023 | Approved | STUART CHAPMAN |
| Wood Frame | 7/28/2023 | Corrections Issued | RAUL BARAJAS |
| Wood Frame | 9/11/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/26/2023 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 9/26/2023 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 9/29/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/10/2023 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 10/10/2023 | Approved | BRIAN SULLIVAN |
| Insulation | 10/10/2023 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 10/10/2023 | Partial Approval | BRIAN SULLIVAN |
| Shower Pan | 10/10/2023 | Corrections Issued | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 10/10/2023 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 10/20/2023 | Approved | STUART CHAPMAN |
| Gas Test | 10/20/2023 | Partial Approval | STUART CHAPMAN |
| Sewer | 10/20/2023 | Approved | STUART CHAPMAN |
| Shower Pan | 10/20/2023 | Approved | STUART CHAPMAN |
| Underground Mechanical | 10/20/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Final | 11/14/2023 | Partial Inspection | STUART CHAPMAN |
| Gas Test | 11/14/2023 | Partial Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 12/21/2023 | Approved | STUART CHAPMAN |
| Final | 12/21/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 12/21/2023 | Approved | STUART CHAPMAN |
| HVAC-Final | 12/21/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 12/21/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 12/21/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 12/21/2023 | Approved | STUART CHAPMAN |
| Final | 2/8/2024 | Partial Inspection | RAUL BARAJAS |
| Service/Power Release | 2/8/2024 | Partial Inspection | RAUL BARAJAS |
| Final | 2/12/2024 | OK to Issue CofO | STUART CHAPMAN |
| Service/Power Release | 2/12/2024 | Approved | STUART CHAPMAN |