321 E 116TH ST 90061

Certificate Information: 321 E 116TH ST 90061

Application / Permit
22010-10000-03421
Plan Check / Job No.
B22LA13573
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 34'X34' ONE STORY ADU AT REAR OF THE PROPERTY (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 3/21/2023
Issuing Office
Current Status
CofO Issued on 8/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2022 APPLICANT
Assigned to Plan Check Engineer 7/13/2022 AUNG SOE
Corrections Issued 7/18/2022 AUNG SOE
Building Plans Picked Up 7/19/2022 APPLICANT
Plan Check Approved 3/21/2023 DANIEL SMILEY
Issued 3/21/2023 APPLICANT
CofO in Progress 8/19/2024 BEN MOLSTAD
CofO Issued 8/19/2024 ANSON MAGLASANG
Permit Finaled 8/19/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/26/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/9/2022 JEANETTE VONG
Sewer availability Cleared 8/9/2022 JEANETTE VONG
Low Impact Development Cleared 3/13/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 3/16/2023 JEANETTE VONG

Contact Information

Contractor Jerahian Araz; Lic. No.: 1045340-B 5730 TROTTERS LANE      RANCHO CUCAMONGA, CA 91701
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/30/2023 Approved JOHN KLARIN
Underground Mechanical 9/15/2023 Partial Approval JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Approved JOHN KLARIN
HVAC-Rough 1/8/2024 Approved JOHN KLARIN
PLUMBING-Rough 1/8/2024 Approved JOHN KLARIN
Insulation 2/1/2024 Corrections Issued JOHN KLARIN
Interior/Exterior Lathing 2/1/2024 Approved JOHN KLARIN
Insulation 2/27/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 2/27/2024 Partial Approval JAMES CHAVEZ
Drywall Nailing 3/14/2024 Approved BEN MOLSTAD
Sewer 4/18/2024 Not Ready for Inspection BEN MOLSTAD
Underground Mechanical 4/18/2024 Not Ready for Inspection BEN MOLSTAD
Underground Mechanical 4/23/2024 Approved BEN MOLSTAD
BUILDING-Rough-Frame 6/13/2024 Partial Approval BEN MOLSTAD
Final 6/13/2024 Corrections Issued BEN MOLSTAD
Green Building Final 6/13/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 6/13/2024 Approved BEN MOLSTAD
MERV13>=Final 6/13/2024 Not Ready for Inspection BEN MOLSTAD
MERV13>=Rough 6/13/2024 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 6/13/2024 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 6/13/2024 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 6/13/2024 Not Ready for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 6/13/2024 Approved BEN MOLSTAD
BUILDING-Rough-Frame 6/18/2024 Approved BEN MOLSTAD
Final 6/18/2024 Corrections Issued BEN MOLSTAD
Green Building Final 6/18/2024 Approved BEN MOLSTAD
MERV13>=Final 6/18/2024 Corrections Issued BEN MOLSTAD
MERV13>=Rough 6/18/2024 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 6/18/2024 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 6/18/2024 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 6/18/2024 Approved BEN MOLSTAD
Final 8/9/2024 Not Ready for Inspection BEN MOLSTAD
MERV13>=Final 8/9/2024 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 8/9/2024 SGSOV Approved BEN MOLSTAD
Service/Power Release 8/9/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 8/16/2024 Approved BEN MOLSTAD
Final 8/16/2024 OK to Issue CofO BEN MOLSTAD
HVAC-Final 8/16/2024 Approved BEN MOLSTAD
PLUMBING-Final 8/16/2024 Approved BEN MOLSTAD
Service/Power Release 8/16/2024 Approved BEN MOLSTAD