9521 S GRAMERCY PL 90047
Certificate Information: 9521 S GRAMERCY PL 90047
- Application / Permit
- 22010-10000-03407
- Plan Check / Job No.
- B22LA13512
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan : CONVERT (E) DETACHED GARAGE TO (N) ADU PER LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 11/25/2022
- Issuing Office
- Current Status
- CofO Issued on 7/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2022 | SERGIO MUNIZ |
| Corrections Issued | 8/6/2022 | SERGIO MUNIZ |
| Plan Check Approved | 11/9/2022 | FARSHAD ALIMOHAMADI |
| Issued | 11/25/2022 | APPLICANT |
| CofO in Progress | 7/17/2023 | ENRIQUE MIRELES |
| CofO in Progress | 7/17/2023 | ENRIQUE MIRELES |
| Permit Finaled | 7/23/2023 | DEROLD HAUFF |
| CofO Issued | 7/23/2023 | DEROLD HAUFF |
| Permit Finaled | 7/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/22/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 8/22/2022 | JEANETTE VONG |
| Construction near power lines | Cleared | 11/2/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Heavenly Investments Inc; Lic. No.: 1030918-B | , |
| Engineer | Fox,, James Gordon; Lic. No.: C21543 | 851 PANORAMA ROAD FULLERTON, CA 92831 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/22/2022 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 12/28/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 12/28/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 12/28/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/23/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/23/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 3/23/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 3/23/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/23/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 3/28/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 4/3/2023 | Approved | JOSEPH MCGARRY |
| Shower Pan | 4/3/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/20/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/3/2023 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/23/2023 | Approved | ENRIQUE MIRELES |
| Gas Test | 6/12/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 6/12/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/27/2023 | Approved | ENRIQUE MIRELES |
| Final | 6/27/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 6/27/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 6/27/2023 | Approved | ENRIQUE MIRELES |
| Final | 7/5/2023 | OK to Issue CofO | ENRIQUE MIRELES |