1343 S COMSTOCK AVE 90024
Certificate Information: 1343 S COMSTOCK AVE 90024
- Application / Permit
- 22010-10000-03391
- Plan Check / Job No.
- B22LA13428
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE AND RECREATION ROOM TO 1-STORY ACCESSORY DWELLING UNIT CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/14/2022
- Issuing Office
- Current Status
- CofO Issued on 4/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2022 | DANIEL YIP |
| Corrections Issued | 7/20/2022 | DANIEL YIP |
| Applicant returned to address corrections | 10/5/2022 | DANIEL YIP |
| Plan Check Approved | 10/11/2022 | DANIEL YIP |
| Issued | 10/14/2022 | APPLICANT |
| CofO in Progress | 4/11/2024 | STEPHANIE SWANSON |
| Permit Finaled | 4/12/2024 | DANIEL ORRANTE |
| CofO Issued | 4/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2022 | DINAH GARIN |
| Sewer availability | Cleared | 7/28/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2022 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 10/6/2022 | ROBERT HUGHES |
Contact Information
| Architect | , ; Lic. No.: C36869 | 1309 KENISTON AVE LOS ANGELES, CA 90019 |
| Contractor | D K R Construction Inc; Lic. No.: 1070450-B | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/6/2023 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 1/24/2023 | Partial Approval | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 1/27/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 1/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 1/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 1/31/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 2/2/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/16/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/24/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/29/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 3/29/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/29/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/15/2023 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 5/15/2023 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/3/2023 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 8/3/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/16/2023 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/16/2023 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/17/2023 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 9/11/2023 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 9/11/2023 | Partial Approval | MICHAEL PELHAM |
| Final | 9/12/2023 | Corrections Issued | MICHAEL PELHAM |
| Insulation | 9/19/2023 | Conditional Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 10/2/2023 | Approved | STEPHANIE SWANSON |
| Insulation | 10/2/2023 | Approved | STEPHANIE SWANSON |
| Gas Test | 2/9/2024 | Approved | MICHAEL PELHAM |
| HVAC-Final | 2/23/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 2/23/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 2/27/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 3/1/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Final | 3/1/2024 | Approved | STEPHANIE SWANSON |
| Special/Order Compliance | 3/7/2024 | Partial Approval | STEPHANIE SWANSON |
| Final | 3/22/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 3/22/2024 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 3/22/2024 | Approved | STEPHANIE SWANSON |
| Final | 4/11/2024 | OK to Issue CofO | STEPHANIE SWANSON |