17920 W CALVERT ST 91316

Certificate Information: 17920 W CALVERT ST 91316

Application / Permit
22010-10000-03385
Plan Check / Job No.
B22LA11889
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
ePlan PROPOSED REC ROOM
Permit Issued
Issued on 5/18/2023
Issuing Office
Current Status
CofO in Progress on 1/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/23/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 SINA KHOSRAVI
Corrections Issued 7/11/2022 SINA KHOSRAVI
Quality Review Completed 7/15/2022 CHARLES CHANG
Applicant returned to address corrections 4/17/2023 SINA KHOSRAVI
Plan Check Approved 5/1/2023 SINA KHOSRAVI
Issued 5/18/2023 APPLICANT
CofO in Progress 5/8/2024 JON MCHUGH
CofO in Progress 6/5/2024 JON MCHUGH
No Progress 1/10/2025 SEAN WIRCH
CofO in Progress 1/10/2025 SEAN WIRCH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/26/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/26/2022 CARLOS AGUILERA
Sewer availability Cleared 7/26/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/9/2022 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/26/2023 Partial Approval JON MCHUGH
Footing/Foundation/Slab 6/13/2023 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Partial Approval JON MCHUGH
Deputy Wood Construction 8/28/2023 Approved JON MCHUGH
PLUMBING-Rough 9/6/2023 Approved JON MCHUGH
Interior/Exterior Lathing 9/21/2023 Partial Approval JON MCHUGH
Wood Frame 10/10/2023 Corrections Issued JON MCHUGH
BUILDING-Rough-Frame 10/18/2023 Partial Approval JON MCHUGH
Shower Pan 10/18/2023 Approved JON MCHUGH
Insulation 10/23/2023 Approved JON MCHUGH
Interior/Exterior Lathing 10/23/2023 Approved JON MCHUGH
BUILDING-Rough-Frame 11/8/2023 Approved JON MCHUGH
Drywall Nailing 11/8/2023 Approved JON MCHUGH
Green Building Rough 11/8/2023 Approved JON MCHUGH
Verify Sprinkler Sign Off 11/8/2023 Approved JON MCHUGH
PLUMBING-Final 2/22/2024 Partial Approval JON MCHUGH
ELECTRICAL-Final 2/26/2024 Corrections Issued JON MCHUGH
Final 5/7/2024 OK to Issue CofO JON MCHUGH
Green Building Final 5/7/2024 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 5/7/2024 SGSOV Approved JON MCHUGH
Service/Power Release 5/7/2024 Not Required JON MCHUGH
Smoke Detectors 5/7/2024 Approved JON MCHUGH
Final 6/5/2024 OK to Issue CofO JON MCHUGH