6556 W BARTON AVE 90038

Certificate Information: 6556 W BARTON AVE 90038

Application / Permit
22010-10000-03381
Plan Check / Job No.
B22LA13350
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Garage and storage room conversion to and second story addition to create a detached ADU per LAMC 12.22A.33(c) and (d)
Permit Issued
Issued on 4/17/2024
Issuing Office
Current Status
CofO Issued on 11/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 MARCELA FRANQUEZ
Corrections Issued 8/13/2022 MARCELA FRANQUEZ
Quality Review Completed 8/19/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 3/29/2023 MARCELA FRANQUEZ
Applicant returned to address corrections 6/30/2023 MARCELA FRANQUEZ
Applicant returned to address corrections 7/6/2023 MARCELA FRANQUEZ
Applicant returned to address corrections 2/28/2024 MARCELA FRANQUEZ
Plan Check Approved 3/22/2024 MARCELA FRANQUEZ
Issued 4/17/2024 APPLICANT
CofO in Progress 11/13/2025 CRAIG VAUGHAN
CofO in Progress 11/14/2025 SCOTT FINNILA
CofO in Progress 11/14/2025 SCOTT FINNILA
CofO in Progress 11/14/2025 SCOTT FINNILA
Permit Finaled 11/16/2025 DEROLD HAUFF
Permit Finaled 11/16/2025 DEROLD HAUFF
CofO Issued 11/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/22/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 8/22/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/25/2022 STEVE MELGAR
Sewer availability Cleared 8/25/2022 STEVE MELGAR
Construction near power lines Cleared 11/18/2022 RIDWAN HARDY
Construction within easement Cleared 12/8/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Xia,, Ji; Lic. No.: NA89014       ,
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/8/2024 Not Ready for Inspection ROY SPAULDING
Footing/Foundation/Slab 12/10/2024 Not Ready for Inspection CRAIG VAUGHAN
METHANE-Barrier 12/10/2024 Not Ready for Inspection CRAIG VAUGHAN
METHANE-Subgrade 12/10/2024 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 12/20/2024 Partial Approval CRAIG VAUGHAN
METHANE-Barrier 12/20/2024 Approved CRAIG VAUGHAN
METHANE-Subgrade 12/20/2024 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 1/2/2025 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 1/2/2025 Partial Approval ROY SPAULDING
Footing/Foundation/Slab 1/7/2025 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 2/5/2025 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/5/2025 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 2/5/2025 Approved ENRIQUE MIRELES
METHANE-Rough 2/5/2025 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/7/2025 Partial Approval CRAIG VAUGHAN
Special/Order Compliance 2/12/2025 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 3/4/2025 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 3/4/2025 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 3/4/2025 Not Ready for Inspection CRAIG VAUGHAN
Pre-Inspection 3/7/2025 Partial Inspection BRIAN SULLIVAN
Special/Order Compliance 3/7/2025 Partial Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 3/11/2025 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/11/2025 Approved CRAIG VAUGHAN
HVAC-Rough 3/11/2025 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 3/11/2025 Corrections Issued CRAIG VAUGHAN
Gas Test 3/21/2025 Partial Approval BRENDAN MORELLI
Insulation 3/21/2025 Corrections Issued BRENDAN MORELLI
Pre-Inspection 3/26/2025 Corrections Issued CRAIG VAUGHAN
Special/Order Compliance 3/26/2025 Partial Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 4/3/2025 Approved CRAIG VAUGHAN
Insulation 4/3/2025 Approved CRAIG VAUGHAN
PLUMBING-Rough 4/3/2025 Partial Approval CRAIG VAUGHAN
Drywall Nailing 4/7/2025 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 4/7/2025 Approved CRAIG VAUGHAN
Shower Pan 4/7/2025 Approved CRAIG VAUGHAN
Final 6/10/2025 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 6/10/2025 Approved CRAIG VAUGHAN
Green Building Final 6/10/2025 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 6/10/2025 Approved CRAIG VAUGHAN
Sewer 7/18/2025 No Access for Inspection CRAIG VAUGHAN
Sewer 7/22/2025 Corrections Issued CRAIG VAUGHAN
Pre-Inspection 7/29/2025 Partial Inspection SCOTT FINNILA
Special/Order Compliance 7/29/2025 Corrections Issued SCOTT FINNILA
Special/Order Compliance 9/23/2025 Partial Inspection RAUL BARAJAS
Final 11/12/2025 OK to Issue CofO CRAIG VAUGHAN