816 1/2 N MCCADDEN PL 90038

Certificate Information: 816 1/2 N MCCADDEN PL 90038

Application / Permit
22010-10000-03373
Plan Check / Job No.
B22LA13345
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (N) ADDITION AND DETACHED GARAGE INTO (N) DETACHED ADU PER ORDIANANCE
Permit Issued
Issued on 6/5/2023
Issuing Office
Metro
Current Status
CofO Issued on 11/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2022 APPLICANT
Assigned to Plan Check Engineer 7/25/2022 RICARDO RAMIREZ
Corrections Issued 7/26/2022 RICARDO RAMIREZ
Plan Check Approved 3/9/2023 FERNANDO FLORES
Issued 6/5/2023 APPLICANT
CofO in Progress 10/30/2023 JOAQUIN GREENOUGH
CofO Issued 11/2/2023 DEROLD HAUFF
Permit Finaled 11/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction within easement Cleared 11/16/2022 RIDWAN HARDY
Address approval Cleared 12/21/2022 CINDY QI
Sewer availability Cleared 12/21/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 12/22/2022 CINDY QI

Contact Information

Contractor U M C Construction Inc; Lic. No.: 1053597-B 9145 CLANCEY AVE      DOWNEY, CA 90240
Engineer Tagudar,, Fred; Lic. No.: C33612 255 W 5TH ST APT 706      SAN PEDRO, CA 90731

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/7/2023 Conditional Approval JOAQUIN GREENOUGH
Pre-Inspection 7/12/2023 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 7/12/2023 Partial Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 7/18/2023 Approved STUART CHAPMAN
Footing/Foundation/Slab 7/18/2023 Approved STUART CHAPMAN
Underground Mechanical 7/28/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 8/8/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 8/8/2023 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 8/8/2023 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 8/8/2023 Partial Approval JOAQUIN GREENOUGH
HVAC-Rough 8/22/2023 Partial Inspection BRIAN SULLIVAN
PLUMBING-Rough 8/22/2023 Partial Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 8/23/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 8/23/2023 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Rough 8/23/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 8/28/2023 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 8/28/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 9/5/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 9/5/2023 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/6/2023 Approved JOAQUIN GREENOUGH
Green Building Rough 9/6/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 9/6/2023 Approved JOAQUIN GREENOUGH
Shower Pan 9/6/2023 Approved JOAQUIN GREENOUGH
Drywall Nailing 9/8/2023 Not Ready for Inspection BRIAN SULLIVAN
Insulation 9/8/2023 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 9/8/2023 Partial Approval BRIAN SULLIVAN
Shower Pan 9/8/2023 Approved BRIAN SULLIVAN
Drywall Nailing 9/13/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 9/13/2023 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 10/19/2023 Not Ready for Inspection STUART CHAPMAN
Final 10/19/2023 Corrections Issued STUART CHAPMAN
Service/Power Release 10/19/2023 Not Ready for Inspection STUART CHAPMAN
Final 10/25/2023 Conditional Approval JOAQUIN GREENOUGH
Green Building Final 10/25/2023 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 10/25/2023 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 10/25/2023 Approved JOAQUIN GREENOUGH
Final 10/30/2023 OK to Issue CofO JOAQUIN GREENOUGH