1448 W 22ND ST 90007
Certificate Information: 1448 W 22ND ST 90007
- Application / Permit
- 22010-10000-03372
- Plan Check / Job No.
- B22LA13343
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW 1STORY 2 UNIT ADU per state law GCS 65852.2(e)(1)(D), WFPP, ADM-2022-7471-ADUH
- Permit Issued
- Issued on 6/14/2023
- Issuing Office
- Current Status
- CofO Issued on 7/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | MICHAEL LOPEZ |
| Corrections Issued | 7/29/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 8/4/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 11/15/2022 | STARR CHEN |
| Plan Check Approved | 12/8/2022 | STARR CHEN |
| Issued | 6/14/2023 | APPLICANT |
| CofO in Progress | 7/1/2024 | JOSEPH MCGARRY |
| Permit Finaled | 7/2/2024 | DEROLD HAUFF |
| CofO Issued | 7/2/2024 | DEROLD HAUFF |
| Permit Finaled | 7/2/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 8/10/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 8/29/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/1/2022 | JEANETTE VONG |
| CPC | Cleared | 10/17/2022 | DEEPEAKA DHALIWAL |
| HPOZ | Cleared | 10/17/2022 | DEEPEAKA DHALIWAL |
| "Q" conditions | Cleared | 10/20/2022 | DANIEL CORONADO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/20/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 11/13/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 11/22/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Rough-Elec/Plmb/HVAC | 2/20/2024 | No Access for Inspection | ARTHUR NEGRETE |
| Wood Frame | 2/20/2024 | No Access for Inspection | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 2/23/2024 | Approved | ARTHUR NEGRETE |
| Wood Frame | 2/23/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 3/4/2024 | Approved | ARTHUR NEGRETE |
| Insulation | 3/12/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 3/12/2024 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 3/20/2024 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 3/20/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 4/1/2024 | Approved | ARTHUR NEGRETE |
| Sewer | 4/1/2024 | Approved | ARTHUR NEGRETE |
| Shower Pan | 4/2/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 5/20/2024 | Approved | WILLIAM KUEHN |
| Final | 5/20/2024 | Corrections Issued | WILLIAM KUEHN |
| Footing/Foundation/Slab | 5/20/2024 | Approved | WILLIAM KUEHN |
| Green Building Final | 5/20/2024 | Corrections Issued | WILLIAM KUEHN |
| Green Building Rough | 5/20/2024 | Approved | WILLIAM KUEHN |
| MERV13>=Final | 5/20/2024 | Approved | WILLIAM KUEHN |
| MERV13>=Rough | 5/20/2024 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 5/20/2024 | SGSOV Not Required | WILLIAM KUEHN |
| Service/Power Release | 5/20/2024 | Corrections Issued | WILLIAM KUEHN |
| Smoke Detectors | 5/20/2024 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 5/20/2024 | Approved | WILLIAM KUEHN |
| Final | 6/13/2024 | Not Ready for Inspection | WILLIAM KUEHN |
| Green Building Final | 6/13/2024 | Partial Inspection | WILLIAM KUEHN |
| Service/Power Release | 6/13/2024 | Not Ready for Inspection | WILLIAM KUEHN |
| Final | 6/24/2024 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 6/24/2024 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 6/24/2024 | Approved | JOSEPH MCGARRY |