1448 W 22ND ST 90007

Certificate Information: 1448 W 22ND ST 90007

Application / Permit
22010-10000-03372
Plan Check / Job No.
B22LA13343
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEW 1STORY 2 UNIT ADU per state law GCS 65852.2(e)(1)(D), WFPP, ADM-2022-7471-ADUH
Permit Issued
Issued on 6/14/2023
Issuing Office
Current Status
CofO Issued on 7/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/9/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 MICHAEL LOPEZ
Corrections Issued 7/29/2022 MICHAEL LOPEZ
Quality Review Completed 8/4/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 11/15/2022 STARR CHEN
Plan Check Approved 12/8/2022 STARR CHEN
Issued 6/14/2023 APPLICANT
CofO in Progress 7/1/2024 JOSEPH MCGARRY
Permit Finaled 7/2/2024 DEROLD HAUFF
CofO Issued 7/2/2024 DEROLD HAUFF
Permit Finaled 7/2/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/9/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/10/2022 JEANETTE VONG
Sewer availability Cleared 8/10/2022 JEANETTE VONG
Low Impact Development Cleared 8/29/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/1/2022 JEANETTE VONG
CPC Cleared 10/17/2022 DEEPEAKA DHALIWAL
HPOZ Cleared 10/17/2022 DEEPEAKA DHALIWAL
"Q" conditions Cleared 10/20/2022 DANIEL CORONADO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/20/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 11/13/2023 Partial Approval KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 11/22/2023 Corrections Issued KATHRYN BUTTERWORTH
Rough-Elec/Plmb/HVAC 2/20/2024 No Access for Inspection ARTHUR NEGRETE
Wood Frame 2/20/2024 No Access for Inspection ARTHUR NEGRETE
Rough-Elec/Plmb/HVAC 2/23/2024 Approved ARTHUR NEGRETE
Wood Frame 2/23/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 3/4/2024 Approved ARTHUR NEGRETE
Insulation 3/12/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 3/12/2024 Approved ARTHUR NEGRETE
Drywall Nailing 3/20/2024 Approved ARTHUR NEGRETE
Underground Mechanical 3/20/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 4/1/2024 Approved ARTHUR NEGRETE
Sewer 4/1/2024 Approved ARTHUR NEGRETE
Shower Pan 4/2/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 5/20/2024 Approved WILLIAM KUEHN
Final 5/20/2024 Corrections Issued WILLIAM KUEHN
Footing/Foundation/Slab 5/20/2024 Approved WILLIAM KUEHN
Green Building Final 5/20/2024 Corrections Issued WILLIAM KUEHN
Green Building Rough 5/20/2024 Approved WILLIAM KUEHN
MERV13>=Final 5/20/2024 Approved WILLIAM KUEHN
MERV13>=Rough 5/20/2024 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Not Required WILLIAM KUEHN
Service/Power Release 5/20/2024 Corrections Issued WILLIAM KUEHN
Smoke Detectors 5/20/2024 Approved WILLIAM KUEHN
Verify Sprinkler Sign Off 5/20/2024 Approved WILLIAM KUEHN
Final 6/13/2024 Not Ready for Inspection WILLIAM KUEHN
Green Building Final 6/13/2024 Partial Inspection WILLIAM KUEHN
Service/Power Release 6/13/2024 Not Ready for Inspection WILLIAM KUEHN
Final 6/24/2024 OK to Issue CofO JOSEPH MCGARRY
Green Building Final 6/24/2024 Approved JOSEPH MCGARRY
Service/Power Release 6/24/2024 Approved JOSEPH MCGARRY