1951 N BEL-AIR ROAD 90077
Certificate Information: 1951 N BEL-AIR ROAD 90077
- Application / Permit
- 22010-10000-03359
- Plan Check / Job No.
- B22LA13263
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- DETACHED REC ROOM WITH ELEVATED DECK AND ROOF DECK The building shall be equipped with an automatic residential fire sprinkler system in accordance with NFPA13R
- Permit Issued
- Issued on 12/22/2022
- Issuing Office
- Valley
- Current Status
- Issued on 12/22/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/21/2022 | MONICA RAMIREZ |
| Corrections Issued | 8/5/2022 | MONICA RAMIREZ |
| Quality Review Completed | 8/8/2022 | RODOLFO ARIAS |
| Building Plans Picked Up | 8/12/2022 | APPLICANT |
| Applicant returned to address corrections | 9/20/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 9/28/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 10/4/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 11/1/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 11/7/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 11/15/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 11/17/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 11/22/2022 | MONICA RAMIREZ |
| Applicant returned to address corrections | 12/20/2022 | MONICA RAMIREZ |
| Plan Check Approved | 12/21/2022 | MONICA RAMIREZ |
| Issued | 12/22/2022 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/23/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 8/23/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 8/23/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 8/23/2022 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 8/23/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 8/23/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2022 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 9/21/2022 | MICHAEL SCADUTO |
| Construction near power lines | Cleared | 9/27/2022 | WALTER RAMIREZ |
| Excavation more than 5-ft deep | Cleared | 11/15/2022 | CALOSHA APPROVED |
| Hydrant and Access approval | Cleared | 11/15/2022 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 11/18/2022 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 12/21/2022 | MONICA RAMIREZ |
| Grading Pre-Inspection | Cleared | 12/21/2022 | MONICA RAMIREZ |
Contact Information
| Architect | Whipple,, Marc Evan; Lic. No.: C17132 | 15233 VENTURA BLVD SUITE PH9 SHERMAN OAKS, CA 91403 |
| Contractor | Tallen & Tyce Development Inc; Lic. No.: 1029383-B | 15260 VENTURA BLVD #845 SHERMAN OAKS, CA 91403 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 2/17/2023 | Conditional Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 2/21/2023 | Conditional Approval | MICHAEL PELHAM |
| Piling/Pier/Caisson | 3/8/2023 | Partial Approval | MICHAEL PELHAM |
| Deputy Other (see comments) | 3/9/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 5/9/2023 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/9/2023 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 5/11/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Other (see comments) | 5/12/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 5/12/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 5/16/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 5/31/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 12/27/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Masonry | 12/27/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Wood Construction | 1/22/2025 | Conditional Approval | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 4/25/2025 | Corrections Issued | STEPHANIE SWANSON |
| Rough-Elec/Plmb/HVAC | 5/8/2025 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 5/8/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Shower Pan | 5/13/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Shower Pan | 5/15/2025 | No Access for Inspection | CHRISTOPHER WILSON |
| Shower Pan | 5/19/2025 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 5/30/2025 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 6/24/2025 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 6/24/2025 | Approved | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 6/24/2025 | Approved | CHRISTOPHER WILSON |
| Insulation | 7/2/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Insulation | 7/9/2025 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 7/11/2025 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 7/17/2025 | Approved | STEPHANIE SWANSON |
| Gas Test | 2/12/2026 | Not Ready for Inspection | EVAN COOPER |