335 1/2 E COLDEN AVE 90003

Certificate Information: 335 1/2 E COLDEN AVE 90003

Application / Permit
22010-10000-03315
Plan Check / Job No.
B22LA13061
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEW DETACHED ADU 468 SF AT REAR OF PROPERTY
Permit Issued
Issued on 3/24/2023
Issuing Office
Current Status
CofO Issued on 2/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2022 APPLICANT
Assigned to Plan Check Engineer 7/13/2022 JOSEPH RAFOLS
Corrections Issued 7/14/2022 JOSEPH RAFOLS
Plan Check Approved 3/23/2023 JOSEPH RAFOLS
Issued 3/24/2023 APPLICANT
CofO in Progress 2/1/2024 JOHN KLARIN
CofO Issued 2/1/2024 ANSON MAGLASANG
Permit Finaled 2/1/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/21/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 7/21/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/10/2023 WALLIE JONG
Sewer availability Cleared 3/14/2023 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/6/2023 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 7/6/2023 Not Ready for Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 7/14/2023 Approved JOHN KLARIN
Pre-Inspection 7/14/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 7/21/2023 Partial Approval JOHN KLARIN
Green Building Rough 7/21/2023 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 7/21/2023 Partial Approval JOHN KLARIN
Verify Sprinkler Sign Off 7/21/2023 Not Ready for Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Partial Approval JOHN KLARIN
Insulation 7/24/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 8/9/2023 Corrections Issued JOHN KLARIN
PLUMBING-Rough 8/9/2023 Corrections Issued JOHN KLARIN
Wood Frame 8/9/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 8/11/2023 Approved JOHN KLARIN
PLUMBING-Rough 8/11/2023 Approved JOHN KLARIN
Insulation 8/15/2023 Approved JOHN KLARIN
Drywall Nailing 8/25/2023 Corrections Issued JAMES CHAVEZ
HVAC-Rough 8/25/2023 Corrections Issued JAMES CHAVEZ
Drywall Nailing 8/31/2023 Approved JOHN KLARIN
HVAC-Rough 8/31/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 9/5/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 9/11/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 10/6/2023 Partial Approval JOHN KLARIN
Final 10/6/2023 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 10/6/2023 Approved JOHN KLARIN
Green Building Final 10/6/2023 Corrections Issued JOHN KLARIN
Green Building Rough 10/6/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 10/6/2023 SGSOV Approved JOHN KLARIN
Service/Power Release 10/6/2023 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 10/6/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 10/6/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/5/2024 Approved JOHN KLARIN
Final 1/5/2024 Corrections Issued JOHN KLARIN
Green Building Final 1/5/2024 Approved JOHN KLARIN
Service/Power Release 1/5/2024 Not Ready for Inspection JOHN KLARIN
Service/Power Release 1/9/2024 Not Ready for Inspection JOHN KLARIN
Final 1/23/2024 Corrections Issued JAMES CHAVEZ
Service/Power Release 1/23/2024 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Final 1/31/2024 Approved JOHN KLARIN
Final 1/31/2024 OK to Issue CofO JOHN KLARIN
HVAC-Final 1/31/2024 Approved JOHN KLARIN
PLUMBING-Final 1/31/2024 Approved JOHN KLARIN
Service/Power Release 1/31/2024 Approved JOHN KLARIN