335 1/2 E COLDEN AVE 90003
Certificate Information: 335 1/2 E COLDEN AVE 90003
- Application / Permit
- 22010-10000-03315
- Plan Check / Job No.
- B22LA13061
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW DETACHED ADU 468 SF AT REAR OF PROPERTY
- Permit Issued
- Issued on 3/24/2023
- Issuing Office
- Current Status
- CofO Issued on 2/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2022 | JOSEPH RAFOLS |
| Corrections Issued | 7/14/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 3/23/2023 | JOSEPH RAFOLS |
| Issued | 3/24/2023 | APPLICANT |
| CofO in Progress | 2/1/2024 | JOHN KLARIN |
| CofO Issued | 2/1/2024 | ANSON MAGLASANG |
| Permit Finaled | 2/1/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/21/2022 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 7/21/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2023 | WALLIE JONG |
| Sewer availability | Cleared | 3/14/2023 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/6/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 7/6/2023 | Not Ready for Inspection | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 7/14/2023 | Approved | JOHN KLARIN |
| Pre-Inspection | 7/14/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/21/2023 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 7/21/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 7/21/2023 | Partial Approval | JOHN KLARIN |
| Verify Sprinkler Sign Off | 7/21/2023 | Not Ready for Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2023 | Partial Approval | JOHN KLARIN |
| Insulation | 7/24/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 8/9/2023 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 8/9/2023 | Corrections Issued | JOHN KLARIN |
| Wood Frame | 8/9/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 8/11/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 8/11/2023 | Approved | JOHN KLARIN |
| Insulation | 8/15/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 8/25/2023 | Corrections Issued | JAMES CHAVEZ |
| HVAC-Rough | 8/25/2023 | Corrections Issued | JAMES CHAVEZ |
| Drywall Nailing | 8/31/2023 | Approved | JOHN KLARIN |
| HVAC-Rough | 8/31/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 9/5/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 9/11/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/6/2023 | Partial Approval | JOHN KLARIN |
| Final | 10/6/2023 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 10/6/2023 | Approved | JOHN KLARIN |
| Green Building Final | 10/6/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 10/6/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 10/6/2023 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 10/6/2023 | Approved | JOHN KLARIN |
| Verify Sprinkler Sign Off | 10/6/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/5/2024 | Approved | JOHN KLARIN |
| Final | 1/5/2024 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 1/5/2024 | Approved | JOHN KLARIN |
| Service/Power Release | 1/5/2024 | Not Ready for Inspection | JOHN KLARIN |
| Service/Power Release | 1/9/2024 | Not Ready for Inspection | JOHN KLARIN |
| Final | 1/23/2024 | Corrections Issued | JAMES CHAVEZ |
| Service/Power Release | 1/23/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Final | 1/31/2024 | Approved | JOHN KLARIN |
| Final | 1/31/2024 | OK to Issue CofO | JOHN KLARIN |
| HVAC-Final | 1/31/2024 | Approved | JOHN KLARIN |
| PLUMBING-Final | 1/31/2024 | Approved | JOHN KLARIN |
| Service/Power Release | 1/31/2024 | Approved | JOHN KLARIN |