3919 W BOYCE AVE 90039
Certificate Information: 3919 W BOYCE AVE 90039
- Application / Permit
- 22010-10000-03299
- Plan Check / Job No.
- B22LA13048
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. 1-story addition to existing single family dwelling at rear.
- Permit Issued
- Issued on 3/10/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | TU HUA |
| Corrections Issued | 8/17/2022 | TU HUA |
| Quality Review Completed | 8/18/2022 | CHAD DOI |
| Applicant returned to address corrections | 11/23/2022 | TU HUA |
| Applicant returned to address corrections | 12/23/2022 | TU HUA |
| Applicant returned to address corrections | 2/17/2023 | TU HUA |
| Plan Check Approved | 3/10/2023 | TU HUA |
| Issued | 3/10/2023 | APPLICANT |
| CofO in Progress | 2/8/2024 | ALIZAH MAYAGOITIA |
| CofO Issued | 2/28/2024 | DEROLD HAUFF |
| Permit Finaled | 2/28/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2022 | WALLIE JONG |
| Sewer availability | Cleared | 8/29/2022 | WALLIE JONG |
| ZI | Cleared | 10/31/2022 | DALIA MOKAYED |
| Low Impact Development | Cleared | 12/22/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 12/27/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/25/2023 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/25/2023 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 3/25/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/25/2023 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 3/30/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 4/4/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/18/2023 | Partial Inspection | SCOTT FINNILA |
| Wood Frame | 4/18/2023 | Partial Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 4/25/2023 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 4/25/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Partial Approval | SCOTT FINNILA |
| Insulation | 5/1/2023 | Conditional Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 7/5/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Special/Order Compliance | 7/12/2023 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/8/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/23/2023 | Partial Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/28/2023 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 9/13/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 9/13/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/13/2023 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/13/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/15/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 9/15/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/22/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/2/2023 | Approved | JOSH MEISTER |
| Underground Mechanical | 10/3/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 10/5/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/17/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 2/1/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/1/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 2/6/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 2/8/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |