11603 W ADDISON ST 91601
Certificate Information: 11603 W ADDISON ST 91601
- Application / Permit
- 22010-10000-03293
- Plan Check / Job No.
- B22VN09126
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- (N) REC ROOM AT THE REAR OF THE LOT
- Permit Issued
- Issued on 1/13/2023
- Issuing Office
- Current Status
- CofO Issued on 10/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | SERGIO GUTIERREZ |
| Corrections Issued | 7/6/2022 | SERGIO GUTIERREZ |
| Quality Review Completed | 7/8/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 12/16/2022 | SERGIO GUTIERREZ |
| Plan Check Approved | 1/10/2023 | SERGIO GUTIERREZ |
| Issued | 1/13/2023 | APPLICANT |
| CofO in Progress | 10/12/2024 | JUAN VALENZUELA |
| Permit Finaled | 10/18/2024 | DANIEL ORRANTE |
| CofO Issued | 10/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/11/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 9/25/2022 | RUEL COLE |
| Low Impact Development | Cleared | 10/12/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/13/2022 | LEE GUILBEAUX |
| Specific Plan | Cleared | 10/13/2022 | CORREY KITCHENS |
| Public Works-Highway Ded. | Cleared | 10/13/2022 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 10/26/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 10/26/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Montemayor,, G F; Lic. No.: C25258 | 1617 S WAVERLY GLEN WAY HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/17/2023 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 3/28/2023 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 5/2/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 5/2/2023 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 5/22/2023 | No Access for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 5/24/2023 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 5/24/2023 | Partial Approval | DAVID MATSON |
| Wood Frame | 6/1/2023 | Approved | JACK KARGODORIAN |
| Insulation | 6/14/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 6/28/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Shower Pan | 6/28/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Drywall Nailing | 7/6/2023 | Approved | JACK KARGODORIAN |
| Shower Pan | 7/6/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 7/11/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/19/2023 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Final | 5/28/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/30/2024 | Partial Approval | JOHN COLEMAN |
| HVAC-Final | 6/6/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 6/6/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/11/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 6/21/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 6/26/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 6/26/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 7/2/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/2/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 7/2/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 10/12/2024 | OK to Issue CofO | JUAN VALENZUELA |
| Service/Power Release | 10/12/2024 | Approved | JUAN VALENZUELA |