519-519 1/2 W 77TH ST 90044

Certificate Information: 519-519 1/2 W 77TH ST 90044

Application / Permit
22010-10000-03283
Plan Check / Job No.
B22LA12973
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan: (N) 2-STORY DUPLEX "A" WITH ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 8/22/2023
Issuing Office
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/5/2022 APPLICANT
Assigned to Plan Check Engineer 7/15/2022 DANIEL YIP
Quality Review Completed 7/21/2022 GARO TELMI
Corrections Issued 7/25/2022 DANIEL YIP
Quality Review Completed 8/3/2022 GARO TELMI
Applicant returned to address corrections 7/3/2023 DANIEL YIP
Plan Check Approved 7/17/2023 DANIEL YIP
Issued 8/22/2023 APPLICANT
CofO in Progress 2/13/2024 ALEJANDRO DE ARTOLA
Permit Finaled 2/22/2024 DEROLD HAUFF
CofO Issued 2/22/2024 DEROLD HAUFF
Permit Finaled 2/22/2024 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 8/2/2022 BRENNEN OBETO
Address approval Cleared 8/10/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 8/12/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 8/12/2022 CHRISTOPHER ROCHA
Opn space landscape/Water mgmt Cleared 8/24/2022 CLAUDE GOODING
Permit Cleared 9/3/2022 CHRISTOPHER ROCHA
Hydrant and Access approval Cleared 9/23/2022 LAVEON RIDER
Low Impact Development Cleared 9/26/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/27/2022 CHRISTOPHER ROCHA
SB8 RUD Cleared 7/10/2023 JESSICA WANG

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/19/2023 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 9/28/2023 Approved MICHAEL LEWIS
Wood Frame 9/28/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Partial Approval MICHAEL LEWIS
Insulation 9/29/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/11/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Approved MICHAEL LEWIS
HVAC-Rough 11/16/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 11/16/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 11/17/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 11/17/2023 Approved MICHAEL LEWIS
MERV13>=Rough 11/17/2023 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 11/17/2023 Approved MICHAEL LEWIS
Insulation 11/20/2023 Approved MICHAEL LEWIS
Drywall Nailing 12/4/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 12/4/2023 Approved MICHAEL LEWIS
Underground Mechanical 12/26/2023 Corrections Issued ANTHONY EGSON
Underground Mechanical 12/28/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 1/10/2024 Approved MICHAEL LEWIS
HVAC-Final 2/8/2024 Approved MICHAEL LEWIS
PLUMBING-Final 2/8/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 2/9/2024 Approved ALEJANDRO DE ARTOLA
Final 2/9/2024 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 2/9/2024 Approved ALEJANDRO DE ARTOLA
MERV13>=Final 2/9/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 2/9/2024 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 2/9/2024 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 2/9/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/12/2024 Approved ALEJANDRO DE ARTOLA
Final 2/12/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 2/12/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 2/12/2024 Approved ALEJANDRO DE ARTOLA
Service/Power Release 2/12/2024 Approved ALEJANDRO DE ARTOLA