8321 S ST ANDREWS PL 90047

Certificate Information: 8321 S ST ANDREWS PL 90047

Application / Permit
22010-10000-03267
Plan Check / Job No.
B22LA12795
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY A.D.U. AT REAR OF LOT PER CA Govt. Code 65852.2(e)(1)(A). CONSTRUCTION PER ENGR OF RECORD
Permit Issued
Issued on 12/5/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2022 APPLICANT
Assigned to Plan Check Engineer 7/11/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 7/13/2022 APPLICANT
Corrections Issued 7/14/2022 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/31/2022 ADAM HEGAZI
Plan Check Approved 10/19/2022 GEORGE ALVAREZ
Issued 12/5/2022 APPLICANT
CofO in Progress 3/3/2025 JOSE MACIAS
CofO Issued 3/12/2025 DEROLD HAUFF
Permit Finaled 3/12/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/4/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/31/2022 WALLIE JONG
Sewer availability Cleared 8/31/2022 WALLIE JONG
Low Impact Development Cleared 9/29/2022 DEBORA LEITE
Construction near power lines Cleared 10/12/2022 OSCAR CASTRO
Roof/Waste drainage to street Cleared 10/18/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/6/2023 Approved ENRIQUE MIRELES
Underground Mechanical 4/17/2023 Corrections Issued ENRIQUE MIRELES
Underground Mechanical 4/25/2023 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 5/10/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 5/10/2023 Not Ready for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 5/30/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 5/30/2023 Not Ready for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/20/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/31/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 10/31/2023 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 1/25/2024 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 1/25/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 1/25/2024 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/23/2024 Not Ready for Inspection JOSE MACIAS
ELECTRICAL-Rough 2/23/2024 Not Ready for Inspection JOSE MACIAS
Green Building Rough 2/23/2024 Not Ready for Inspection JOSE MACIAS
PLUMBING-Rough 2/23/2024 Corrections Issued JOSE MACIAS
Verify Sprinkler Sign Off 2/23/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 5/8/2024 Approved JOSE MACIAS
PLUMBING-Rough 5/8/2024 Approved JOSE MACIAS
HVAC-Rough 8/8/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 8/8/2024 Approved JOSE MACIAS
Special/Order Compliance 8/8/2024 Partial Inspection ALEX COLIN
Insulation 8/13/2024 Corrections Issued JOSE MACIAS
Insulation 8/22/2024 Approved ALEX COLIN
Drywall Nailing 9/9/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 12/16/2024 Approved AMIR NAZARIAN
Final 12/16/2024 Corrections Issued AMIR NAZARIAN
Footing/Foundation/Slab 12/16/2024 Approved AMIR NAZARIAN
Green Building Final 12/16/2024 Corrections Issued AMIR NAZARIAN
Green Building Rough 12/16/2024 Approved AMIR NAZARIAN
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Not Ready AMIR NAZARIAN
Service/Power Release 12/16/2024 Not Ready for Inspection AMIR NAZARIAN
Smoke Detectors 12/16/2024 Approved AMIR NAZARIAN
Final 1/22/2025 Corrections Issued BARRY HACHE
Green Building Final 1/22/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 1/22/2025 SGSOV Not Ready BARRY HACHE
Service/Power Release 1/22/2025 Not Ready for Inspection BARRY HACHE
Final 2/3/2025 No Access for Inspection JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 2/3/2025 SGSOV Approved JOSE MACIAS
Service/Power Release 2/3/2025 Not Ready for Inspection JOSE MACIAS
Final 2/18/2025 Not Ready for Inspection SABAS ALONSO
Service/Power Release 2/18/2025 Not Ready for Inspection SABAS ALONSO
Final 2/26/2025 OK to Issue CofO JOSE MACIAS
Service/Power Release 2/26/2025 Approved JOSE MACIAS