8321 S ST ANDREWS PL 90047
Certificate Information: 8321 S ST ANDREWS PL 90047
- Application / Permit
- 22010-10000-03267
- Plan Check / Job No.
- B22LA12795
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY A.D.U. AT REAR OF LOT PER CA Govt. Code 65852.2(e)(1)(A). CONSTRUCTION PER ENGR OF RECORD
- Permit Issued
- Issued on 12/5/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 7/13/2022 | APPLICANT |
| Corrections Issued | 7/14/2022 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 8/31/2022 | ADAM HEGAZI |
| Plan Check Approved | 10/19/2022 | GEORGE ALVAREZ |
| Issued | 12/5/2022 | APPLICANT |
| CofO in Progress | 3/3/2025 | JOSE MACIAS |
| CofO Issued | 3/12/2025 | DEROLD HAUFF |
| Permit Finaled | 3/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/4/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2022 | WALLIE JONG |
| Sewer availability | Cleared | 8/31/2022 | WALLIE JONG |
| Low Impact Development | Cleared | 9/29/2022 | DEBORA LEITE |
| Construction near power lines | Cleared | 10/12/2022 | OSCAR CASTRO |
| Roof/Waste drainage to street | Cleared | 10/18/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 4/6/2023 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 4/17/2023 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 4/25/2023 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 5/10/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/10/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 5/30/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/30/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 6/20/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/31/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/25/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/25/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/23/2024 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 2/23/2024 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Rough | 2/23/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 2/23/2024 | Corrections Issued | JOSE MACIAS |
| Verify Sprinkler Sign Off | 2/23/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 5/8/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 5/8/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 8/8/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 8/8/2024 | Approved | JOSE MACIAS |
| Special/Order Compliance | 8/8/2024 | Partial Inspection | ALEX COLIN |
| Insulation | 8/13/2024 | Corrections Issued | JOSE MACIAS |
| Insulation | 8/22/2024 | Approved | ALEX COLIN |
| Drywall Nailing | 9/9/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 12/16/2024 | Approved | AMIR NAZARIAN |
| Final | 12/16/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 12/16/2024 | Approved | AMIR NAZARIAN |
| Green Building Final | 12/16/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 12/16/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 12/16/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| Service/Power Release | 12/16/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Smoke Detectors | 12/16/2024 | Approved | AMIR NAZARIAN |
| Final | 1/22/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 1/22/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 1/22/2025 | SGSOV Not Ready | BARRY HACHE |
| Service/Power Release | 1/22/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 2/3/2025 | No Access for Inspection | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 2/3/2025 | Not Ready for Inspection | JOSE MACIAS |
| Final | 2/18/2025 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 2/18/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 2/26/2025 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 2/26/2025 | Approved | JOSE MACIAS |