5727 N MAMMOTH AVE 91401

Certificate Information: 5727 N MAMMOTH AVE 91401

Application / Permit
22010-10000-03233
Plan Check / Job No.
B22LA12635
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY A.D.U. AT REAR OF LOT PER STATE LAW.
Permit Issued
Issued on 11/18/2022
Issuing Office
Valley
Current Status
Issued on 11/18/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/29/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 LAWRENCE QUIRANTE
Corrections Issued 6/30/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 7/7/2022 APPLICANT
Plan Check Approved 7/19/2022 JOSEPH RAFOLS
Issued 11/18/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/2/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 7/2/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 7/8/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/22/2022 DAGOVERTO GUERRERO

Contact Information

Contractor National Pools Inc; Lic. No.: 963509-B 15439 MONTE ST      SYLMAR, CA 91342
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/23/2022 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 12/6/2022 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Partial Approval RYAN SALAZAR
Green Building Rough 1/23/2023 Not Ready for Inspection RYAN SALAZAR
Verify Sprinkler Sign Off 1/23/2023 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 3/6/2023 Approved RYAN SALAZAR
PLUMBING-Rough 3/6/2023 Corrections Issued RYAN SALAZAR
PLUMBING-Rough 4/19/2023 Approved RYAN SALAZAR
Sewer 4/19/2023 Approved RYAN SALAZAR
Insulation 5/30/2023 Approved RYAN SALAZAR
Shower Pan 5/30/2023 Approved RYAN SALAZAR
Drywall Nailing 6/15/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 9/11/2023 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 9/20/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 12/20/2023 Approved RYAN SALAZAR
Final 12/20/2023 Corrections Issued RYAN SALAZAR
Green Building Final 12/20/2023 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 12/20/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/20/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 12/20/2023 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 12/20/2023 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 12/20/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 7/2/2025 Approved RYAN SALAZAR
Final 7/2/2025 Corrections Issued RYAN SALAZAR
PLUMBING-Final 7/2/2025 Approved RYAN SALAZAR
Final 9/29/2025 Partial Approval RYAN SALAZAR
Green Building Final 9/29/2025 Approved RYAN SALAZAR
Service/Power Release 9/29/2025 Approved RYAN SALAZAR