709 N CHESTNUT AVE 90042

Certificate Information: 709 N CHESTNUT AVE 90042

Application / Permit
22010-10000-03229
Plan Check / Job No.
B22LA12595
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. New Factory-Built Two-Bedroom Dwelling Unit per RADCO Approved FBH Plan RAD-31-1029 (Duplex Building Permit: B21LA12173, 21010-10000-03246)
Permit Issued
Issued on 1/31/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 PRANITA SHAH
Corrections Issued 7/20/2022 PRANITA SHAH
Quality Review Completed 7/29/2022 MICHAEL PEREZ
Plan Check Approved 12/14/2022 SERGIO GUTIERREZ
Issued 1/31/2023 APPLICANT
CofO in Progress 5/3/2024 ALIZAH MAYAGOITIA
CofO Issued 5/8/2024 DEROLD HAUFF
Permit Finaled 5/8/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/28/2022 CELINA MORENO
Highway dedication Cleared 7/28/2022 CELINA MORENO
Permit Cleared 7/28/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/29/2022 CELINA MORENO
Sewer availability Cleared 7/29/2022 CELINA MORENO
Low Impact Development Cleared 8/9/2022 CHRIS VONG
Miscellaneous Cleared 8/10/2022 MAXFIELD VERMY
Roof/Waste drainage to street Cleared 8/11/2022 CELINA MORENO
Hydrant and Access approval Cleared 8/27/2022 RUEL COLE
GPI Written Notices Cleared 12/14/2022 PRANITA SHAH
Grading Pre-Inspection Cleared 12/14/2022 PRANITA SHAH

Contact Information

Contractor Weinstock Construction Llc; Lic. No.: 1099736-B 137 N LARCHMONT BLVD #237      LOS ANGELES, CA 90004
Engineer Sveiven,, Shane; Lic. No.: C89133 1909 S ALMA STREET      SAN PEDRO, CA 90731
Engineer Tsalyuk,, Yefim; Lic. No.: C52871 11278 LOS ALAMITOS BLVD 354      LOS ALAMITOS, CA 90720
Engineer Wendt,, Randal; Lic. No.: GE2341 842 COE ST      CAMARILLO, CA 93010

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/9/2023 Approved CRAIG VAUGHAN
Grading Pre-Inspection 6/21/2023 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 11/13/2023 Approved ROY SPAULDING
BUILDING-Rough-Frame 12/6/2023 Partial Approval ROY SPAULDING
Green Building Rough 12/6/2023 Approved ROY SPAULDING
MERV13>=Rough 12/6/2023 Approved ROY SPAULDING
Verify Sprinkler Sign Off 12/6/2023 Approved ROY SPAULDING
PLUMBING-Rough 1/5/2024 Approved ROY SPAULDING
ELECTRICAL-Rough 1/9/2024 Approved ROY SPAULDING
HVAC-Rough 1/9/2024 Approved ROY SPAULDING
Underground Mechanical 1/29/2024 Approved ROY SPAULDING
PLUMBING-Final 2/20/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 3/12/2024 Approved ROY SPAULDING
HVAC-Final 3/22/2024 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Final 3/29/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/2/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 5/2/2024 Approved ALIZAH MAYAGOITIA
Final 5/2/2024 OK to Issue CofO ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/2/2024 Approved ALIZAH MAYAGOITIA
Green Building Final 5/2/2024 Approved ALIZAH MAYAGOITIA
MERV13>=Final 5/2/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/2/2024 SGSOV Not Required ALIZAH MAYAGOITIA
Service/Power Release 5/2/2024 Approved ALIZAH MAYAGOITIA
Smoke Detectors 5/2/2024 Approved ALIZAH MAYAGOITIA