727 1/2 N HARPER AVE 90046
Certificate Information: 727 1/2 N HARPER AVE 90046
- Application / Permit
- 22010-10000-03222
- Plan Check / Job No.
- B22LA12578
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY ADU PER LAMC 12.22 A.33 (c)-(d) WITH ATTACHED PATIO COVER
- Permit Issued
- Issued on 3/8/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 7/20/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/29/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 8/1/2022 | APPLICANT |
| Plan Check Approved | 3/8/2023 | TEODORO DIAZ RODRIGUEZ |
| Issued | 3/8/2023 | APPLICANT |
| CofO in Progress | 12/26/2024 | JOSE MACIAS |
| No Progress | 1/11/2025 | DEROLD HAUFF |
| CofO in Progress | 1/11/2025 | DEROLD HAUFF |
| Permit Finaled | 1/26/2025 | DEROLD HAUFF |
| CofO Issued | 1/26/2025 | DEROLD HAUFF |
| Permit Finaled | 1/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/30/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 9/1/2022 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 10/30/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 11/3/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 11/7/2022 | CHRISTOPHER ROCHA |
| Construction near power lines | Cleared | 1/23/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/24/2023 | Conditional Approval | LILIANA PORTILLO |
| Sewer | 5/24/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 5/24/2023 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/30/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/16/2023 | Partial Approval | LILIANA PORTILLO |
| Deputy Wood Construction | 11/7/2023 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/9/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 11/9/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 11/9/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/14/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 11/14/2023 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/11/2024 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Rough | 1/11/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 1/17/2024 | Approved | LILIANA PORTILLO |
| Green Building Rough | 1/17/2024 | Approved | LILIANA PORTILLO |
| Insulation | 1/17/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/17/2024 | Partial Approval | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 1/17/2024 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 1/23/2024 | Approved | AMIR NAZARIAN |
| Shower Pan | 2/26/2024 | Approved | RICHARD DOCKUS |
| Final | 6/18/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 6/18/2024 | Corrections Issued | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 6/18/2024 | SGSOV Approved | AMIR NAZARIAN |
| Service/Power Release | 6/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Smoke Detectors | 6/18/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 7/16/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 7/16/2024 | Approved | AMIR NAZARIAN |
| Service/Power Release | 7/16/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Smoke Detectors | 7/16/2024 | Approved | AMIR NAZARIAN |
| Final | 8/16/2024 | Conditional Approval | AMIR NAZARIAN |
| Service/Power Release | 8/16/2024 | Approved | AMIR NAZARIAN |
| Special/Order Compliance | 8/19/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 9/25/2024 | Corrections Issued | JOSE MACIAS |
| Final | 11/18/2024 | Not Ready for Inspection | JOSE MACIAS |
| Final | 11/22/2024 | Conditional Approval | JOSE MACIAS |
| Service/Power Release | 11/22/2024 | Approved | JOSE MACIAS |
| Final | 12/24/2024 | OK to Issue CofO | JOSE MACIAS |