5411 S HILLCREST DR 90043

Certificate Information: 5411 S HILLCREST DR 90043

Application / Permit
22010-10000-03175
Plan Check / Job No.
B22LA12383
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLan NEW TWO STORY DETACHED ADU WITH STORAGE. DETACHED ADU PER LAMC 12.22 A.33 (c) and (d)
Permit Issued
Issued on 10/5/2023
Issuing Office
Current Status
Issued on 10/5/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/27/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 ADRIANA LOPEZ
Corrections Issued 8/11/2022 ADRIANA LOPEZ
Quality Review Completed 8/12/2022 GARO TELMI
Applicant returned to address corrections 7/11/2023 ADRIANA LOPEZ
Applicant returned to address corrections 8/4/2023 ADRIANA LOPEZ
Plan Check Approved 9/12/2023 ADRIANA LOPEZ
Issued 10/5/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/4/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 11/7/2022 ABEL CASILLAS
Sewer availability Cleared 11/7/2022 ABEL CASILLAS
Low Impact Development Cleared 2/14/2023 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/26/2023 ADRIAN SANCHEZ

Contact Information

Contractor Trinity Contracting Concepts Inc; Lic. No.: 1001565-B       ,
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/12/2023 Approved ANTHONY EGSON
Footing/Foundation/Slab 12/12/2023 Conditional Approval ANTHONY EGSON
PLUMBING-Rough 12/12/2023 Partial Approval ANTHONY EGSON
Special/Order Compliance 12/12/2023 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 2/1/2024 Partial Inspection ANTHONY EGSON
Insulation 2/1/2024 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Partial Approval BRENDAN MORELLI
Insulation 2/13/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 3/8/2024 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Partial Approval ANTHONY EGSON
Deputy Wood Construction 4/9/2024 Approved ANTHONY EGSON
ELECTRICAL-Rough 4/18/2024 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 5/30/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/30/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 9/24/2024 Approved ANTHONY EGSON
PLUMBING-Rough 9/24/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 10/10/2024 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Approved ANTHONY EGSON
Green Building Rough 10/10/2024 Approved ANTHONY EGSON
HVAC-Rough 10/10/2024 Approved ANTHONY EGSON
Insulation 10/25/2024 Approved ALEX COLIN
Drywall Nailing 11/8/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 11/8/2024 Partial Approval JOSH MEISTER
Shower Pan 11/8/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 7/23/2025 Approved LUIS CASTRO
Service/Power Release 7/23/2025 Not Ready for Inspection LUIS CASTRO
BUILDING-Rough-Frame 8/15/2025 Approved LUIS CASTRO
Final 8/15/2025 Not Ready for Inspection LUIS CASTRO
Footing/Foundation/Slab 8/15/2025 Approved LUIS CASTRO
Green Building Final 8/15/2025 Not Ready for Inspection LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Approved LUIS CASTRO
Service/Power Release 8/15/2025 Corrections Issued LUIS CASTRO
Smoke Detectors 8/15/2025 Not Ready for Inspection LUIS CASTRO
Verify Sprinkler Sign Off 8/15/2025 Approved LUIS CASTRO