3428 1/2 N CHADWICK DR 90032

Certificate Information: 3428 1/2 N CHADWICK DR 90032

Application / Permit
22010-10000-03172
Plan Check / Job No.
B22LA12379
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW 1-STORY DETACHED (29' X 24'-3") ADU (703 SF) PER LAMC 12.22A.33(c)-(d). ALL CONSTRUCTION PER WFPP.
Permit Issued
Issued on 2/22/2023
Issuing Office
Current Status
CofO Issued on 8/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 VIVIAN LAO
Corrections Issued 7/15/2022 VIVIAN LAO
Applicant returned to address corrections 8/18/2022 VIVIAN LAO
Applicant returned to address corrections 12/6/2022 VIVIAN LAO
Plan Check Approved 12/8/2022 VIVIAN LAO
Plan Check Approved 12/8/2022 ANSINEE TOWNSEND
Issued 2/22/2023 APPLICANT
CofO in Progress 8/21/2025 LILIANA PORTILLO
Permit Finaled 8/23/2025 DEROLD HAUFF
CofO Issued 8/23/2025 DEROLD HAUFF
Permit Finaled 8/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/19/2022 CELINA MORENO
Grading Pre-Inspection Cleared 8/23/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 8/24/2022 CELINA MORENO
Sewer availability Cleared 8/24/2022 CELINA MORENO
Low Impact Development Cleared 11/9/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 11/10/2022 CELINA MORENO
GPI Written Notices Cleared 11/29/2022 VIVIAN LAO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/28/2023 Not Ready for Inspection RUBEN SALAS
Excavation/Setback/Form/Re-Bar 4/4/2023 Approved AMY COLIN
PLUMBING-Rough 8/24/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 11/8/2023 No Access for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/20/2023 Approved ROY SPAULDING
HVAC-Rough 11/20/2023 Corrections Issued ROY SPAULDING
PLUMBING-Rough 11/20/2023 Approved ROY SPAULDING
ELECTRICAL-Rough 11/29/2023 No Access for Inspection AMY COLIN
HVAC-Rough 11/29/2023 No Access for Inspection AMY COLIN
Interior/Exterior Lathing 11/29/2023 No Access for Inspection AMY COLIN
PLUMBING-Rough 11/29/2023 Corrections Issued AMY COLIN
ELECTRICAL-Rough 12/1/2023 Approved AMY COLIN
HVAC-Rough 12/1/2023 Approved AMY COLIN
Interior/Exterior Lathing 12/1/2023 Partial Approval AMY COLIN
PLUMBING-Rough 12/1/2023 Approved AMY COLIN
Gas Test 12/20/2023 Approved AMY COLIN
Insulation 12/20/2023 Approved AMY COLIN
Interior/Exterior Lathing 12/20/2023 Approved AMY COLIN
Drywall Nailing 12/27/2023 Approved AMY COLIN
Green Building Rough 12/27/2023 Approved AMY COLIN
Shower Pan 1/19/2024 Approved AMY COLIN
Underground Mechanical 4/9/2024 Partial Approval BRENDAN MORELLI
Underground Mechanical 7/23/2024 Partial Approval LILIANA PORTILLO
ELECTRICAL-Final 10/10/2024 Corrections Issued JOHN QUINTANILLA
ELECTRICAL-Final 10/23/2024 Corrections Issued LILIANA PORTILLO
Service/Power Release 10/23/2024 Not Ready for Inspection LILIANA PORTILLO
Final 12/10/2024 Corrections Issued LILIANA PORTILLO
Service/Power Release 12/10/2024 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 2/14/2025 Approved LILIANA PORTILLO
Final 2/14/2025 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 2/14/2025 Approved LILIANA PORTILLO
Green Building Final 2/14/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 2/14/2025 SGSOV Not Ready LILIANA PORTILLO
Service/Power Release 2/14/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 2/14/2025 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 2/14/2025 Approved LILIANA PORTILLO
HVAC-Final 5/1/2025 Corrections Issued LILIANA PORTILLO
Final 7/25/2025 Corrections Issued BRENDAN MORELLI
Green Building Final 7/25/2025 Not Ready for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV Not Ready BRENDAN MORELLI
Service/Power Release 7/25/2025 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Final 8/20/2025 Approved LILIANA PORTILLO
Final 8/20/2025 OK to Issue CofO LILIANA PORTILLO
Green Building Final 8/20/2025 Approved LILIANA PORTILLO
HVAC-Final 8/20/2025 Approved LILIANA PORTILLO
PLUMBING-Final 8/20/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 8/20/2025 SGSOV Approved LILIANA PORTILLO
Service/Power Release 8/20/2025 Approved LILIANA PORTILLO