3748-3750 N BERRY DR 91604

Certificate Information: 3748-3750 N BERRY DR 91604

Application / Permit
22010-10000-03156
Plan Check / Job No.
B22LA12367
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLan NEW 2-STORY SFD OVER BASEMENT WITH ATTACHED ADU AND GARAGE
Permit Issued
Issued on 3/6/2023
Issuing Office
Current Status
CofO Issued on 5/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/27/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 JAD BASMA
Corrections Issued 7/16/2022 JAD BASMA
Quality Review Completed 7/28/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 8/23/2022 JAD BASMA
Applicant returned to address corrections 9/9/2022 JAD BASMA
Applicant returned to address corrections 10/12/2022 JAD BASMA
Plan Check Approved 2/13/2023 JAD BASMA
Plan Check Approved 2/14/2023 JAD BASMA
Issued 3/6/2023 APPLICANT
CofO in Progress 3/19/2025 CHRISTOPHE COCHRAN
Permit Finaled 5/2/2025 RUBEN SALAS
CofO Issued 5/2/2025 RUBEN SALAS
Permit Finaled 5/2/2025 RUBEN SALAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/4/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/4/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 8/8/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/22/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 10/12/2022 LEE GUILBEAUX
Address approval Cleared 10/13/2022 LEE GUILBEAUX
Miscellaneous Cleared 10/13/2022 LEE GUILBEAUX
Hydrant and Access approval Cleared 10/25/2022 RUEL COLE
BHO/Hillside ordinance Cleared 11/14/2022 LEE GUILBEAUX
Sewer availability Cleared 11/14/2022 LEE GUILBEAUX
Low Impact Development Cleared 1/12/2023 CHRIS VONG
Roof/Waste drainage to street Cleared 1/13/2023 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 1/31/2023 LEE GUILBEAUX
Permit Cleared 2/2/2023 JOSE DUARTE-DIAZ
GPI Written Notices Cleared 2/13/2023 JAD BASMA
Grading Pre-Inspection Cleared 2/13/2023 JAD BASMA
Miscellaneous Cleared 2/13/2023 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/13/2023 Approved JOHN COLEMAN
Deputy Grading 3/20/2023 Conditional Approval JUAN VALENZUELA
Deputy Grading 3/24/2023 Partial Approval MICHAEL TEMPLE
Deputy Grading 3/28/2023 Conditional Approval JUAN VALENZUELA
Piling/Pier/Caisson 4/5/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Piling/Pier/Caisson 4/7/2023 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 4/11/2023 Conditional Approval MICHAEL SMITH
Piling/Pier/Caisson 4/18/2023 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 4/19/2023 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 5/1/2023 Conditional Approval DAVID MATSON
Deputy Reinf. Concrete 5/9/2023 Conditional Approval JUAN VALENZUELA
Piling/Pier/Caisson 6/9/2023 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/6/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 7/6/2023 Partial Approval CHRISTOPHE COCHRAN
Reinforced Concrete Frame 7/20/2023 Off-Hour Fees Due
Reinforced Concrete Frame 7/20/2023 Partial Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 7/24/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Reinforced Concrete Frame 7/24/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Reinforced Concrete Frame 7/28/2023 Partial Approval CHRISTOPHE COCHRAN
Reinforced Concrete Frame 8/2/2023 Partial Approval CHRISTOPHE COCHRAN
Deputy Shotcrete 8/7/2023 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 8/16/2023 Conditional Approval JUAN VALENZUELA
Reinforced Concrete Frame 8/16/2023 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/18/2023 Off-Hour Fees Due
Footing/Foundation/Slab 8/18/2023 Partial Approval JUAN VALENZUELA
Reinforced Concrete Frame 8/18/2023 Off-Hour Fees Due
Verify Sprinkler Sign Off 8/18/2023 Off-Hour Fees Due
Reinforced Concrete Frame 9/7/2023 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 9/8/2023 Conditional Approval JUAN VALENZUELA
Deputy Steel/Welding 9/28/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 9/28/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Steel/Welding 9/29/2023 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 9/29/2023 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 11/7/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/16/2023 Corrections Issued JOHN COLEMAN
Verify Sprinkler Sign Off 11/16/2023 Corrections Issued JOHN COLEMAN
Wood Frame 11/16/2023 Corrections Issued JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 Partial Approval CHRISTOPHE COCHRAN
Wood Frame 12/8/2023 Partial Approval CHRISTOPHE COCHRAN
HVAC-Rough 1/25/2024 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 1/25/2024 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/26/2024 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 1/26/2024 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 1/26/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/30/2024 Approved CHRISTOPHE COCHRAN
Shower Pan 2/2/2024 Not Ready for Inspection THOMAS FINNILA
Shower Pan 2/7/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 2/12/2024 Partial Approval MISAEL ESPARZA
Piling/Pier/Caisson 3/13/2024 Partial Inspection JOHN COLEMAN
Piling/Pier/Caisson 3/18/2024 Partial Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 3/21/2024 Partial Approval CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/29/2024 Partial Approval CHRISTOPHE COCHRAN
Insulation 4/4/2024 Corrections Issued CHRISTOPHE COCHRAN
Insulation 4/8/2024 Approved CHRISTOPHE COCHRAN
Drywall Nailing 4/23/2024 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/11/2024 Partial Approval JUAN VALENZUELA
Service/Power Release 9/12/2024 Corrections Issued CHRISTOPHE COCHRAN
Pre-Inspection 10/25/2024 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 1/7/2025 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/27/2025 Approved CHRISTOPHE COCHRAN
Final 1/27/2025 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 1/27/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 1/27/2025 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 1/27/2025 SGSOV Not Ready CHRISTOPHE COCHRAN
Service/Power Release 1/27/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 1/27/2025 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 2/6/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 3/12/2025 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV Not Ready JACK KARGODORIAN
Service/Power Release 3/12/2025 Not Ready for Inspection JACK KARGODORIAN
Final 3/17/2025 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/17/2025 SGSOV Not Ready JACK KARGODORIAN
Service/Power Release 3/17/2025 Approved JACK KARGODORIAN
Final 3/19/2025 OK to Issue CofO CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 3/19/2025 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 3/19/2025 Approved CHRISTOPHE COCHRAN