5208 W SANCHEZ DR 90008

Certificate Information: 5208 W SANCHEZ DR 90008

Application / Permit
22010-10000-03154
Plan Check / Job No.
B22LA12365
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLan New 2-Story SFD with basement
Permit Issued
Issued on 1/25/2023
Issuing Office
Current Status
CofO in Progress on 5/31/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/7/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 JAD BASMA
Corrections Issued 7/25/2022 JAD BASMA
Quality Review Completed 8/3/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 8/31/2022 JAD BASMA
Plan Check Approved 1/13/2023 JAD BASMA
Issued 1/25/2023 APPLICANT
CofO in Progress 5/26/2026 LUIS CASTRO
No Progress 5/31/2026 DEROLD HAUFF
CofO in Progress 5/31/2026 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 8/31/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 9/6/2022 STEVE MELGAR
Sewer availability Cleared 9/6/2022 STEVE MELGAR
Hydrant and Access approval Cleared 9/13/2022 GILBERT URREA
Trees in Parkway Cleared 10/18/2022 ADALBERTO VERA
Low Impact Development Cleared 10/24/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 10/25/2022 STEVE MELGAR
GPI Written Notices Cleared 1/10/2023 JAD BASMA
Grading Pre-Inspection Cleared 1/10/2023 JAD BASMA
Miscellaneous Cleared 1/10/2023 KIRK LINKLATER

Contact Information

Architect Manish, Desai Architect; Lic. No.: NA10632       ,
Contractor Gaia Construction Inc; Lic. No.: 912485-B       ,
Engineer Tuchscher,, James Todd; Lic. No.: NA77649       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/8/2023 Approved STUART CHAPMAN
Underground Mechanical 12/1/2023 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 12/18/2023 Partial Approval ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 1/25/2024 Partial Approval ANTHONY EGSON
Reinforced Concrete Frame 1/25/2024 Approved ANTHONY EGSON
Footing/Foundation/Slab 1/26/2024 No Access for Inspection ANTHONY EGSON
Reinforced Concrete Frame 1/26/2024 No Access for Inspection ANTHONY EGSON
Deputy Shotcrete 1/29/2024 Approved ANTHONY EGSON
Deputy Drilled-In Anchors 2/29/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 4/23/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 4/25/2024 Not Ready for Inspection ANTHONY EGSON
Reinforced Concrete Frame 4/25/2024 Not Ready for Inspection ANTHONY EGSON
Sewer 4/25/2024 Partial Approval ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 4/29/2024 Partial Approval ANTHONY EGSON
Deputy Reinf. Concrete 5/2/2024 Approved ANTHONY EGSON
Masonry Wall/Backfill 5/20/2024 Approved ANTHONY EGSON
Reinforced Concrete Frame 5/20/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 9/9/2024 Partial Approval ANTHONY EGSON
Underground Mechanical 10/29/2024 Corrections Issued BARRY HACHE
PLUMBING-Rough 10/31/2024 Approved BARRY HACHE
Underground Mechanical 10/31/2024 Approved BARRY HACHE
HVAC-Rough 12/6/2024 Corrections Issued BARRY HACHE
HVAC-Rough 12/10/2024 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 1/15/2025 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 1/24/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 2/6/2025 Partial Approval LUIS CASTRO
Green Building Rough 2/6/2025 Partial Approval LUIS CASTRO
Special/Order Compliance 2/6/2025 Conditional Approval RAUL BARAJAS
Verify Sprinkler Sign Off 2/6/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 3/6/2025 Partial Approval LUIS CASTRO
Insulation 3/7/2025 Partial Approval ALEX COLIN
Shower Pan 3/11/2025 Approved LUIS CASTRO
Drywall Nailing 3/21/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 3/21/2025 Approved REGINA MENDEZ
ELECTRICAL-Final 12/5/2025 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Final 1/7/2026 Partial Approval LUIS CASTRO
PLUMBING-Final 2/19/2026 Approved LUIS CASTRO
HVAC-Final 3/2/2026 Corrections Issued LUIS CASTRO
Gas Test 3/6/2026 Approved LUIS CASTRO
HVAC-Final 3/6/2026 Approved LUIS CASTRO
PLUMBING-Rough 3/6/2026 Approved LUIS CASTRO
BUILDING-Rough-Frame 5/22/2026 Approved LUIS CASTRO
ELECTRICAL-Final 5/22/2026 Approved LUIS CASTRO
Final 5/22/2026 OK to Issue CofO LUIS CASTRO
Footing/Foundation/Slab 5/22/2026 Approved LUIS CASTRO
Green Building Final 5/22/2026 Approved LUIS CASTRO
Green Building Rough 5/22/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 5/22/2026 SGSOV Approved LUIS CASTRO
Service/Power Release 5/22/2026 Approved LUIS CASTRO
Smoke Detectors 5/22/2026 Approved LUIS CASTRO