12034 W OTSEGO ST 91607
Certificate Information: 12034 W OTSEGO ST 91607
- Application / Permit
- 22010-10000-03117
- Plan Check / Job No.
- B22VN07104
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- ePlan. New 12'x19'6" cover patio.
- Permit Issued
- Issued on 12/19/2022
- Issuing Office
- Current Status
- CofO Corrected on 2/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | TU HUA |
| Corrections Issued | 6/22/2022 | TU HUA |
| Quality Review Completed | 6/23/2022 | CHAD DOI |
| Applicant returned to address corrections | 11/30/2022 | TU HUA |
| Applicant returned to address corrections | 12/1/2022 | TU HUA |
| Applicant returned to address corrections | 12/15/2022 | TU HUA |
| Applicant returned to address corrections | 12/16/2022 | TU HUA |
| Plan Check Approved | 12/16/2022 | TU HUA |
| Issued | 12/19/2022 | APPLICANT |
| CofO in Progress | 11/7/2023 | JOHN COLEMAN |
| CofO Issued-Status Void | 1/17/2024 | RUBEN SALAS |
| Permit Finaled-Status Void | 1/17/2024 | RUBEN SALAS |
| Re-Activate Permit | 1/31/2024 | RUBEN SALAS |
| CofO Corrected | 2/1/2024 | RUBEN SALAS |
| Permit Finaled | 2/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 7/14/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/14/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 8/5/2022 | KURT CORRAL |
| Specific Plan | Cleared | 8/30/2022 | CORREY KITCHENS |
| ZI | Cleared | 8/30/2022 | CORREY KITCHENS |
| Low Impact Development | Cleared | 10/26/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 10/27/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/27/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/3/2023 | Approved | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 2/7/2023 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 4/28/2023 | Partial Approval | JOHN COLEMAN |
| ELECTRICAL-Rough | 4/28/2023 | Approved | JOHN COLEMAN |
| Green Building Rough | 4/28/2023 | Not Ready for Inspection | JOHN COLEMAN |
| HVAC-Rough | 4/28/2023 | Not Ready for Inspection | JOHN COLEMAN |
| PLUMBING-Rough | 4/28/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 4/28/2023 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 10/31/2023 | Approved | JOHN COLEMAN |
| Drywall Nailing | 10/31/2023 | Partial Inspection | JOHN COLEMAN |
| Final | 10/31/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Footing/Foundation/Slab | 10/31/2023 | Approved | JOHN COLEMAN |
| Green Building Final | 10/31/2023 | Partial Inspection | JOHN COLEMAN |
| Green Building Rough | 10/31/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 10/31/2023 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 10/31/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Smoke Detectors | 10/31/2023 | Approved | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 10/31/2023 | Approved | JOHN COLEMAN |
| Drywall Nailing | 11/3/2023 | Approved | JOHN COLEMAN |
| Final | 11/3/2023 | Partial Approval | JOHN COLEMAN |
| Green Building Final | 11/3/2023 | Approved | JOHN COLEMAN |
| Service/Power Release | 11/3/2023 | Approved | JOHN COLEMAN |