1627 E 92ND ST 1-18 90002

Certificate Information: 1627 E 92ND ST 1-18 90002

Application / Permit
22010-10000-03107
Plan Check / Job No.
B22LA12032
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3 STORY 18 UNITS (100% AFFORDABLE HOUSING) APARTMENT TO INCLUDE 3 STORY TYPE VA APARTMENT, TIER 4 TOC WITH BASE INCENTIVES ONLY.
Permit Issued
Issued on 6/19/2024
Issuing Office
Current Status
CofO Issued on 9/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 MANUEL MONTUFAR
Corrections Issued 7/13/2022 MANUEL MONTUFAR
Quality Review Completed 7/18/2022 EUGENE BARBEAU
Applicant returned to address corrections 9/8/2022 MANUEL MONTUFAR
Applicant returned to address corrections 9/9/2022 MANUEL MONTUFAR
Applicant returned to address corrections 9/20/2022 MANUEL MONTUFAR
Plan Check Approved 8/16/2023 MANUEL MONTUFAR
Issued 6/19/2024 APPLICANT
CofO in Progress 9/30/2025 RAFAEL ESPINOZA
Permit Finaled 9/30/2025 ERNESTO CORRAL
CofO Issued 9/30/2025 ERNESTO CORRAL
Permit Finaled 9/30/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 7/23/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 7/26/2022 CHRISTOPHER ROCHA
Trees in Parkway Cleared 7/27/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 10/2/2022 RUEL COLE
Fire Marshal Fire Life Safety Cleared 2/7/2023 MENOA AGHAJANI
Highway dedication Cleared 2/21/2023 TREVOR QUAN
Permit Cleared 2/21/2023 TREVOR QUAN
Low Impact Development Cleared 3/14/2023 ORVAL HERNANDEZ-MARCI
Density Bonus 12.22.A.31 Cleared 3/21/2023 NICHOLAS KAWAZOE
SB8 RUD Cleared 3/21/2023 NICHOLAS KAWAZOE
Frnt yard landscape/Water mgmt Cleared 4/18/2023 RYAN LY
Miscellaneous Cleared 4/18/2023 RYAN LY
Opn space landscape/Water mgmt Cleared 4/18/2023 RYAN LY
Roof/Waste drainage to street Cleared 4/18/2023 CHRISTOPHER ROCHA
DAS Clearance Cleared 5/23/2023 MANUEL MONTUFAR
Sewer availability Cleared 7/3/2023 CHRISTOPHER ROCHA
Green Code Cleared 7/21/2023 MANUEL MONTUFAR

Contact Information

Contractor R S C Construction Inc; Lic. No.: 1059714-B 3617 W 107TH STREET      INGLEWOOD, CA 90303
Contractor Rsc Construction, Inc; Lic. No.: 1059714-B 3617 W 107TH STREET      INGLEWOOD, CA 90303
Engineer Parvini,, Mehdi; Lic. No.: C63186 1226 SOUZA DRIVE      EL DORADO HILLS, CA 95762
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Landscape Architect Savage,, Michael Sanford; Lic. No.: LA4397 1125 SHEPPARD DRIVE      FULLERTON, CA 92831

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 8/9/2024 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 8/9/2024 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 8/14/2024 Partial Approval ALFREDO LOPEZ
Footing/Foundation/Slab 8/14/2024 Partial Approval ALFREDO LOPEZ
Deputy Wood Construction 8/22/2024 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/22/2024 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/29/2024 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Partial Inspection DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Partial Approval RAFAEL ESPINOZA
Wood Frame 9/18/2024 Partial Approval RAFAEL ESPINOZA
Insulation 10/29/2024 Corrections Issued RAFAEL CORTES
Green Building Rough 11/1/2024 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 11/1/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 11/1/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/7/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 12/3/2024 Partial Approval RAFAEL ESPINOZA
Green Building Rough 1/30/2025 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 1/30/2025 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 1/30/2025 Not Ready for Inspection RAFAEL ESPINOZA
Green Building Rough 1/31/2025 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 1/31/2025 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 1/31/2025 Partial Approval RAFAEL ESPINOZA
Insulation 2/7/2025 No Access for Inspection RAFAEL CORTES
Insulation 2/11/2025 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 2/19/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 2/24/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 2/27/2025 Partial Approval RAFAEL ESPINOZA
Final 7/11/2025 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 7/11/2025 Approved RAFAEL ESPINOZA
Pre-Inspection 9/12/2025 Corrections Issued RAFAEL ESPINOZA
Final 9/22/2025 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 9/22/2025 Approved RAFAEL ESPINOZA
Green Building Final 9/22/2025 Approved RAFAEL ESPINOZA
Green Building Rough 9/22/2025 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 9/22/2025 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 9/22/2025 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 9/22/2025 Approved RAFAEL ESPINOZA
Wood Frame 9/22/2025 Not Ready for Inspection RAFAEL ESPINOZA
Final 9/24/2025 OK to Issue CofO RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 9/24/2025 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 9/24/2025 Approved RAFAEL ESPINOZA
Special/Order Compliance 9/24/2025 Approved RAFAEL ESPINOZA
Wood Frame 9/24/2025 Partial Inspection RAFAEL ESPINOZA
Wood Frame 9/30/2025 Approved RAFAEL ESPINOZA