16844 W ADDISON ST 91436

Certificate Information: 16844 W ADDISON ST 91436

Application / Permit
22010-10000-03089
Plan Check / Job No.
B22LA11901
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan New one-story A.D.U with attached coverred patio PER STATE LAW
Permit Issued
Issued on 9/7/2022
Issuing Office
Current Status
CofO Issued on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2022 APPLICANT
Assigned to Plan Check Engineer 6/28/2022 KHUONG TRUONG
Corrections Issued 6/28/2022 KHUONG TRUONG
Applicant returned to address corrections 9/6/2022 KHUONG TRUONG
Plan Check Approved 9/7/2022 KHUONG TRUONG
Issued 9/7/2022 APPLICANT
CofO in Progress 6/16/2023 VINCENT HANLEY
Permit Finaled 8/23/2023 JOHN JANSON
CofO Issued 8/23/2023 JOHN JANSON
Permit Finaled 8/23/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/4/2022 LEE GUILBEAUX
Low Impact Development Cleared 8/4/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 8/4/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/8/2022 LEE GUILBEAUX
Sewer availability Cleared 8/8/2022 LEE GUILBEAUX
Construction near power lines Cleared 8/18/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/9/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 9/9/2022 Approved VINCENT HANLEY
PLUMBING-Rough 9/9/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/7/2022 Partial Approval VINCENT HANLEY
HVAC-Rough 11/2/2022 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 11/9/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 11/9/2022 Approved VINCENT HANLEY
PLUMBING-Rough 11/9/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 11/9/2022 Approved VINCENT HANLEY
Insulation 11/16/2022 Not Ready for Inspection VINCENT HANLEY
Interior/Exterior Lathing 11/16/2022 Not Ready for Inspection VINCENT HANLEY
Shower Pan 11/16/2022 Approved VINCENT HANLEY
Drywall Nailing 11/28/2022 Approved JESUS PINEDA
Insulation 11/28/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 11/28/2022 Approved JESUS PINEDA
Final 5/9/2023 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/9/2023 SGSOV Approved VINCENT HANLEY
Service/Power Release 5/9/2023 Approved VINCENT HANLEY
Smoke Detectors 5/9/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 6/13/2023 Approved VINCENT HANLEY
Final 6/13/2023 Corrections Issued VINCENT HANLEY
HVAC-Final 6/13/2023 Approved VINCENT HANLEY
PLUMBING-Final 6/13/2023 Approved VINCENT HANLEY
Final 6/16/2023 OK to Issue CofO VINCENT HANLEY