16844 W ADDISON ST 91436
Certificate Information: 16844 W ADDISON ST 91436
- Application / Permit
- 22010-10000-03089
- Plan Check / Job No.
- B22LA11901
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New one-story A.D.U with attached coverred patio PER STATE LAW
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2022 | KHUONG TRUONG |
| Corrections Issued | 6/28/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 9/6/2022 | KHUONG TRUONG |
| Plan Check Approved | 9/7/2022 | KHUONG TRUONG |
| Issued | 9/7/2022 | APPLICANT |
| CofO in Progress | 6/16/2023 | VINCENT HANLEY |
| Permit Finaled | 8/23/2023 | JOHN JANSON |
| CofO Issued | 8/23/2023 | JOHN JANSON |
| Permit Finaled | 8/23/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/4/2022 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 8/4/2022 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/4/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/8/2022 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 8/18/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/9/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 9/9/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 9/9/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 11/2/2022 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/9/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 11/9/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 11/9/2022 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 11/9/2022 | Approved | VINCENT HANLEY |
| Insulation | 11/16/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/16/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Shower Pan | 11/16/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 11/28/2022 | Approved | JESUS PINEDA |
| Insulation | 11/28/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 11/28/2022 | Approved | JESUS PINEDA |
| Final | 5/9/2023 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/9/2023 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 5/9/2023 | Approved | VINCENT HANLEY |
| Smoke Detectors | 5/9/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/13/2023 | Approved | VINCENT HANLEY |
| Final | 6/13/2023 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 6/13/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 6/13/2023 | Approved | VINCENT HANLEY |
| Final | 6/16/2023 | OK to Issue CofO | VINCENT HANLEY |