13005 W DICKENS ST 91604
Certificate Information: 13005 W DICKENS ST 91604
- Application / Permit
- 22010-10000-03084
- Plan Check / Job No.
- B22LA11899
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan :(E) DETACHED GARAGE CONVERSION TO (N) ACCESSORY DWELLING UNIT PER CA GOVT CODE 65852.2(e)(1)(A). NO CHANGE OF (E) FOOTPRINT
- Permit Issued
- Issued on 4/11/2023
- Issuing Office
- Current Status
- CofO Issued on 12/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | HANS SANTIAGO |
| Corrections Issued | 7/14/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 11/11/2022 | HANS SANTIAGO |
| Plan Check Approved | 11/23/2022 | ANDREW SANTIAGO |
| Issued | 4/11/2023 | APPLICANT |
| CofO in Progress | 10/11/2023 | CHRISTOPHE COCHRAN |
| Permit Finaled | 12/8/2023 | RUBEN SALAS |
| CofO Issued | 12/8/2023 | RUBEN SALAS |
| Permit Finaled | 12/8/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 8/9/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2022 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 9/25/2022 | RUEL COLE |
| Construction within easement | Cleared | 10/24/2022 | RIDWAN HARDY |
| ZI | Cleared | 10/28/2022 | JASON CHAN |
| Grading Pre-Inspection | Cleared | 11/21/2022 | KIRK LINKLATER |
Contact Information
| Architect | Brumer,, Aaron Jason; Lic. No.: NA30005 | , |
| Contractor | Owner-Builder | , |
| Engineer | Pachunuri,, Nalin Kumar; Lic. No.: C78970 | 21126 INGOMAR CT CANOGA PARK, CA 91304 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 4/19/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Sewer | 4/19/2023 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 4/19/2023 | Approved | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 4/25/2023 | Conditional Approval | MICHAEL SMITH |
| Deputy Drilled-In Anchors | 5/3/2023 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 5/10/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/10/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 5/16/2023 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/16/2023 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 6/13/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Rough | 6/13/2023 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 6/13/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 6/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/28/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 6/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 6/28/2023 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/13/2023 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 7/13/2023 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 7/25/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 8/3/2023 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 8/3/2023 | Approved | CHRISTOPHE COCHRAN |
| Final | 10/2/2023 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/2/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 10/2/2023 | Approved | MISAEL ESPARZA |
| Final | 10/11/2023 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 10/11/2023 | SGSOV Approved | CHRISTOPHE COCHRAN |