15867 W ASILOMAR BLVD 90272

Certificate Information: 15867 W ASILOMAR BLVD 90272

Application / Permit
22010-10000-03044
Plan Check / Job No.
B22LA11749
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU 799 SQ FT.
Permit Issued
Issued on 7/21/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2022 APPLICANT
Assigned to Plan Check Engineer 6/22/2022 JOSEPH RAFOLS
Corrections Issued 6/22/2022 JOSEPH RAFOLS
Building Plans Picked Up 6/23/2022 APPLICANT
Plan Check Approved 1/27/2023 KHUONG TRUONG
Issued 7/21/2023 APPLICANT
CofO in Progress 11/15/2024 EVAN COOPER
Permit Finaled 11/19/2024 RICHARD STEINBACH
CofO Issued 11/19/2024 RICHARD STEINBACH
Permit Finaled 11/19/2024 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/27/2022 ROBERT HUGHES
Low Impact Development Cleared 8/18/2022 MITESH PATEL
Address approval Cleared 10/4/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 10/12/2022 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 10/12/2022 CATHERINE ADROVER
Sewer availability Cleared 10/12/2022 CATHERINE ADROVER
Coastal Zone Cleared 1/27/2023 DALIA MOKAYED
GPI Written Notices Cleared 1/27/2023 JOSEPH RAFOLS
Miscellaneous Cleared 1/27/2023 DALIA MOKAYED

Contact Information

Contractor J L M Development; Lic. No.: 1025019-B 984 MONUMENT STREET   SUITE 102    PACIFIC PALISADES, CA 90272
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/12/2024 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 1/12/2024 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/19/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 1/19/2024 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 1/24/2024 Approved EVAN COOPER
PLUMBING-Rough 2/16/2024 Partial Approval EVAN COOPER
Sewer 2/16/2024 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Partial Approval EVAN COOPER
PLUMBING-Rough 3/6/2024 Approved EVAN COOPER
HVAC-Rough 3/12/2024 Approved EVAN COOPER
Interior/Exterior Lathing 3/22/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 4/1/2024 Approved EVAN COOPER
BUILDING-Rough-Frame 4/12/2024 Approved EVAN COOPER
Green Building Rough 4/12/2024 Approved EVAN COOPER
Verify Sprinkler Sign Off 4/12/2024 Approved EVAN COOPER
Insulation 4/17/2024 Approved EVAN COOPER
Shower Pan 4/17/2024 Approved EVAN COOPER
Drywall Nailing 4/22/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 4/22/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 6/6/2024 Conditional Approval EVAN COOPER
Final 6/6/2024 Corrections Issued EVAN COOPER
HVAC-Final 6/6/2024 Approved EVAN COOPER
PLUMBING-Final 6/6/2024 Approved EVAN COOPER
Service/Power Release 8/26/2024 Approved EVAN COOPER
Service/Power Release 9/17/2024 Approved EVAN COOPER
Final 11/15/2024 OK to Issue CofO EVAN COOPER
Footing/Foundation/Slab 11/15/2024 Approved EVAN COOPER
Green Building Final 11/15/2024 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 11/15/2024 SGSOV Approved EVAN COOPER
Smoke Detectors 11/15/2024 Approved EVAN COOPER