15867 W ASILOMAR BLVD 90272
Certificate Information: 15867 W ASILOMAR BLVD 90272
- Application / Permit
- 22010-10000-03044
- Plan Check / Job No.
- B22LA11749
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU 799 SQ FT.
- Permit Issued
- Issued on 7/21/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2022 | JOSEPH RAFOLS |
| Corrections Issued | 6/22/2022 | JOSEPH RAFOLS |
| Building Plans Picked Up | 6/23/2022 | APPLICANT |
| Plan Check Approved | 1/27/2023 | KHUONG TRUONG |
| Issued | 7/21/2023 | APPLICANT |
| CofO in Progress | 11/15/2024 | EVAN COOPER |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
| CofO Issued | 11/19/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/27/2022 | ROBERT HUGHES |
| Low Impact Development | Cleared | 8/18/2022 | MITESH PATEL |
| Address approval | Cleared | 10/4/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2022 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 10/12/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 10/12/2022 | CATHERINE ADROVER |
| Coastal Zone | Cleared | 1/27/2023 | DALIA MOKAYED |
| GPI Written Notices | Cleared | 1/27/2023 | JOSEPH RAFOLS |
| Miscellaneous | Cleared | 1/27/2023 | DALIA MOKAYED |
Contact Information
| Contractor | J L M Development; Lic. No.: 1025019-B | 984 MONUMENT STREET SUITE 102 PACIFIC PALISADES, CA 90272 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/12/2024 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/12/2024 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 1/19/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 1/19/2024 | Corrections Issued | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 1/24/2024 | Approved | EVAN COOPER |
| PLUMBING-Rough | 2/16/2024 | Partial Approval | EVAN COOPER |
| Sewer | 2/16/2024 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 3/6/2024 | Approved | EVAN COOPER |
| HVAC-Rough | 3/12/2024 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/22/2024 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 4/1/2024 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 4/12/2024 | Approved | EVAN COOPER |
| Green Building Rough | 4/12/2024 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 4/12/2024 | Approved | EVAN COOPER |
| Insulation | 4/17/2024 | Approved | EVAN COOPER |
| Shower Pan | 4/17/2024 | Approved | EVAN COOPER |
| Drywall Nailing | 4/22/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/22/2024 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Final | 6/6/2024 | Conditional Approval | EVAN COOPER |
| Final | 6/6/2024 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 6/6/2024 | Approved | EVAN COOPER |
| PLUMBING-Final | 6/6/2024 | Approved | EVAN COOPER |
| Service/Power Release | 8/26/2024 | Approved | EVAN COOPER |
| Service/Power Release | 9/17/2024 | Approved | EVAN COOPER |
| Final | 11/15/2024 | OK to Issue CofO | EVAN COOPER |
| Footing/Foundation/Slab | 11/15/2024 | Approved | EVAN COOPER |
| Green Building Final | 11/15/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 11/15/2024 | Approved | EVAN COOPER |