2000 N LINCOLN PARK AVE 90031
Certificate Information: 2000 N LINCOLN PARK AVE 90031
- Application / Permit
- 22010-10000-03028
- Plan Check / Job No.
- B22LA11662
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 7 STORY 184 UNITS (47VLI =25.5%) AFFORDABLE HOUSING APARMENT TO INCLUDE 5 STORY TYPE IIIA APARTMENT OVER 2 STORY TYPE IA APARTMENT / PARKING GARAGE, 12.22 A 25 WITH ADDITIONAL INCENTIVES PER 12.24 U 26
- Permit Issued
- No
- Current Status
- Verifications in Progress on 8/24/2023
Permit Application Status History
Submitted | 7/20/2022 | APPLICANT |
Assigned to Plan Check Engineer | 8/4/2022 | MANUEL MONTUFAR |
Corrections Issued | 8/10/2022 | MANUEL MONTUFAR |
Quality Review Completed | 8/10/2022 | EUGENE BARBEAU |
Applicant returned to address corrections | 8/15/2022 | MANUEL MONTUFAR |
Applicant returned to address corrections | 8/23/2022 | MANUEL MONTUFAR |
Applicant returned to address corrections | 9/26/2022 | MANUEL MONTUFAR |
Applicant returned to address corrections | 9/28/2022 | MANUEL MONTUFAR |
Applicant returned to address corrections | 8/14/2023 | MANUEL MONTUFAR |
Applicant returned to address corrections | 8/16/2023 | MANUEL MONTUFAR |
Applicant returned to address corrections | 8/24/2023 | MANUEL MONTUFAR |
Permit Application Clearance Information
Construction near power lines | Not Cleared | 8/10/2022 | Department of Water and Power |
Density Bonus | Not Cleared | 8/10/2022 | Los Angeles Housing Department |
Frnt yard landscape/Water mgmt | Not Cleared | 8/10/2022 | City Planning Department |
Low Impact Development | Not Cleared | 8/10/2022 | Bureau of Sanitation |
Miscellaneous | Not Cleared | 8/10/2022 | City Planning Department |
Miscellaneous | Not Cleared | 8/10/2022 | City Planning Department |
Opn space landscape/Water mgmt | Not Cleared | 8/10/2022 | City Planning Department |
Roof/Waste drainage to street | Not Cleared | 8/10/2022 | Bureau of Engineering |
Sewer availability | Not Cleared | 8/10/2022 | Bureau of Engineering |
ZA Case | Not Cleared | 8/10/2022 | City Planning Department |
ZA Case | Not Cleared | 8/10/2022 | City Planning Department |
Address approval | Cleared | 10/4/2022 | WALLIE JONG |
Hydrant and Access approval | Cleared | 2/22/2023 | KURT CORRAL |
CPC | Not Cleared | 5/17/2023 | City Planning Department |
Bicycle Parking | Cleared | 6/1/2023 | KATHERINE MENDOZA |
Encroachment in public way | Cleared | 6/1/2023 | KATHERINE MENDOZA |
Eng Process Fee Ord 176,300 | Cleared | 6/21/2023 | JOSEPH RHYU |
Fire Marshal Fire Life Safety | Cleared | 7/27/2023 | ANDREW KO |
Green Code | Cleared | 8/1/2023 | AARON COSTA |
Trees in Parkway | Cleared | 8/8/2023 | ADALBERTO VERA |
Building over 36-ft | Cleared | 8/10/2023 | CALOSHA APPROVED |
Excavation more than 5-ft deep | Cleared | 8/10/2023 | CALOSHA APPROVED |
GPI Written Notices | Cleared | 8/10/2023 | MANUEL MONTUFAR |
Grading Pre-Inspection | Cleared | 8/10/2023 | MANUEL MONTUFAR |
Highway dedication | Cleared | 8/11/2023 | ADRIAN SANCHEZ |
Driveway location | Cleared | 8/18/2023 | MOHAMMAD HASAN |
DAS Clearance | Cleared | 9/25/2023 | ELIZABETH TOMS |
Permit | Cleared | 1/4/2024 | ADRIAN SANCHEZ |
Contact Information
No Data Available. |
Inspector Information
No Data Available. |
Pending Inspections
No Data Available. |
Inspection Request History
No Data Available. |