4811 E TEMPLETON ST 90032
Certificate Information: 4811 E TEMPLETON ST 90032
- Application / Permit
- 22010-10000-03021
- Plan Check / Job No.
- B22LA11629
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ADU 750 SF (2 BEDROOMS AND 2 BATHS) PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND(g) PV to be under separate permit
- Permit Issued
- Issued on 6/2/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | DANIEL SANJUAN |
| Corrections Issued | 6/21/2022 | DANIEL SANJUAN |
| Building Plans Picked Up | 6/27/2022 | APPLICANT |
| Applicant returned to address corrections | 5/9/2023 | MICHAEL LANZONE |
| Plan Check Approved | 5/22/2023 | LUKE GONZALES |
| Issued | 6/2/2023 | APPLICANT |
| CofO in Progress | 12/10/2024 | LILIANA PORTILLO |
| Permit Finaled | 12/18/2024 | DEROLD HAUFF |
| CofO Issued | 12/18/2024 | DEROLD HAUFF |
| Permit Finaled | 12/18/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 10/22/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 3/20/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 3/21/2023 | JEANETTE VONG |
| "Q" conditions | Cleared | 5/8/2023 | JASON CHAN |
| Grading Pre-Inspection | Cleared | 5/18/2023 | SERGIO VALENZUELA |
| "D" conditions | Cleared | 5/22/2023 | RYAN LY |
Contact Information
| Contractor | Mac Construction; Lic. No.: 1059544-B | 4926 CEDAR AVE EL MONTE, CA 91732 |
| Engineer | Wong,, George Voon; Lic. No.: C49894 | 516 N MOORE AVE E MONTEREY PARK, CA 91754 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/7/2023 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 7/14/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 8/15/2023 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2023 | Partial Approval | AMY COLIN |
| Green Building Rough | 9/11/2023 | Not Ready for Inspection | AMY COLIN |
| Verify Sprinkler Sign Off | 9/11/2023 | Not Ready for Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | AMY COLIN |
| Rough-Elec/Plmb/HVAC | 10/12/2023 | Approved | AMY COLIN |
| Verify Sprinkler Sign Off | 10/12/2023 | Approved | AMY COLIN |
| Insulation | 10/19/2023 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 10/24/2023 | Partial Approval | AMY COLIN |
| Drywall Nailing | 11/13/2023 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/13/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 11/30/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 1/16/2024 | No Access for Inspection | AMY COLIN |
| Sewer | 1/30/2024 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 2/14/2024 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/16/2024 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/29/2024 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Final | 9/12/2024 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Final | 9/12/2024 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 9/12/2024 | Approved | BRENDAN MORELLI |
| Final | 10/7/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 10/7/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/7/2024 | SGSOV Not Required | LILIANA PORTILLO |
| Service/Power Release | 10/7/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 10/7/2024 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 11/14/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/27/2024 | Approved | LILIANA PORTILLO |
| Final | 11/27/2024 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 11/27/2024 | Approved | LILIANA PORTILLO |
| HVAC-Final | 11/27/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 11/27/2024 | Approved | LILIANA PORTILLO |
| Service/Power Release | 11/27/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 12/9/2024 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 12/9/2024 | Approved | LILIANA PORTILLO |